scope-check【效率与协作】Analyze a feature or sprint for scope creep by comparing current scope against the original plan. Flags additions, quantifies bloat, and recommends cuts.
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
When this skill is invoked:
Read the original plan — Find the relevant document:
design/gdd/production/sprints/production/milestones/Read the current state — Check what has actually been implemented or is in progress:
Compare original vs current scope:
## Scope Check: [Feature/Sprint Name]
Generated: [Date]
### Original Scope
[List of items from the original plan]
### Current Scope
[List of items currently implemented or in progress]
### Scope Additions (not in original plan)
| Addition | Who Added | When | Justified? | Effort |
|----------|-----------|------|------------|--------|
| [item] | [commit/person] | [date] | [Yes/No/Unclear] | [S/M/L] |
### Scope Removals (in original but dropped)
| Removed Item | Reason | Impact |
|-------------|--------|--------|
| [item] | [why removed] | [what's affected] |
### Bloat Score
- Original items: [N]
- Current items: [N]
- Items added: [N] (+[X]%)
- Items removed: [N]
- Net scope change: [+/-N] ([X]%)
### Risk Assessment
- **Schedule Risk**: [Low/Medium/High] — [explanation]
- **Quality Risk**: [Low/Medium/High] — [explanation]
- **Integration Risk**: [Low/Medium/High] — [explanation]
### Recommendations
1. **Cut**: [Items that should be removed to stay on schedule]
2. **Defer**: [Items that can move to a future sprint/version]
3. **Keep**: [Additions that are genuinely necessary]
4. **Flag**: [Items that need a decision from producer/creative-director]
Output the scope check with a clear verdict: