gantt-planner【设计与创意】Generate interactive HTML Gantt charts with Critical Path Method (CPM) analysis from task lists and dependencies, highlighting the critical path and calculating float times. Use when the user asks to create a Gantt chart, schedule project tasks, analyze the critical path, visualize dependencies, or mentions project timelines, milestones, or task sche…
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Automatically performs Critical Path Method (CPM) analysis on task lists and their dependencies, generating interactive HTML Gantt charts. Supports zooming, critical path filtering, hover details, and dependency arrow visualization.
Simplest usage — pass JSON directly:
python3 scripts/gantt_generator.py --json '{
"project": "New Product Launch",
"tasks": [
{"id": "T1", "name": "Requirements Analysis", "duration": 5, "dependencies": []},
{"id": "T2", "name": "UI Design", "duration": 4, "dependencies": ["T1"]},
{"id": "T3", "name": "Backend Development", "duration": 8, "dependencies": ["T1"]},
{"id": "T4", "name": "Frontend Development", "duration": 6, "dependencies": ["T2"]},
{"id": "T5", "name": "Integration Testing", "duration": 3, "dependencies": ["T3", "T4"]},
{"id": "T6", "name": "Deployment", "duration": 2, "dependencies": ["T5"]}
]
}' --output gantt.html
Read from a file with a specified start date:
python3 scripts/gantt_generator.py --file tasks.json --start-date 2026-05-01 --output gantt.html
| Term | Abbreviation | Meaning |
|---|---|---|
| Earliest Start | ES | The earliest point at which a task can begin |
| Earliest Finish | EF | The earliest point at which a task can be completed (ES + Duration) |
| Latest Start | LS | The latest a task can start without delaying the project |
| Latest Finish | LF | The latest a task can finish without delaying the project |
| Total Float | TF | LS − ES; the number of days a task can be delayed |
| Critical Path | — | The sequence of tasks with zero float, determining the project's minimum duration |
ES = max(EF of all predecessors)EF = ES + DurationLF = min(LS of all successors)LS = LF - DurationA JSON object with the following fields:
{
"project": "Project Name",
"start_date": "2026-05-01",
"tasks": [
{
"id": "T1",
"name": "Task Name",
"duration": 5,
"dependencies": ["T0"]
}
]
}
| Field | Required | Type | Description |
|---|---|---|---|
| project | No | string | Project title; defaults to "Project Gantt Chart" |
| start_date | No | string | YYYY-MM-DD format; can be overridden by the CLI --start-date flag |
| tasks | Yes | array | List of tasks |
| tasks[].id | Yes | string | Unique task identifier |
| tasks[].name | Yes | string | Task name |
| tasks[].duration | Yes | number | Duration in days; must be > 0 |
| tasks[].dependencies | No | array | List of predecessor task IDs; defaults to [] |
The generated HTML file is fully self-contained (no external dependencies) and includes the following interactive features:
python3 scripts/gantt_generator.py [options]
Required (one of):
--json TEXT Task data as a JSON string
--file PATH Path to a JSON file containing task data
Optional:
--start-date DATE Project start date (YYYY-MM-DD); defaults to today
--output, -o PATH Output HTML file path; defaults to stdout
--title TEXT Override the project title
{
"project": "CRM System v2.0 Development",
"start_date": "2026-05-05",
"tasks": [
{"id": "A", "name": "Requirements Research", "duration": 5, "dependencies": []},
{"id": "B", "name": "Architecture Design", "duration": 3, "dependencies": ["A"]},
{"id": "C", "name": "UI/UX Design", "duration": 4, "dependencies": ["A"]},
{"id": "D", "name": "Database Design", "duration": 2, "dependencies": ["B"]},
{"id": "E", "name": "Backend API Development", "duration": 10, "dependencies": ["D"]},
{"id": "F", "name": "Frontend Development", "duration": 8, "dependencies": ["C", "D"]},
{"id": "G", "name": "Unit Testing", "duration": 3, "dependencies": ["E"]},
{"id": "H", "name": "Integration Testing", "duration": 4, "dependencies": ["F", "G"]},
{"id": "I", "name": "User Acceptance Testing", "duration": 3, "dependencies": ["H"]},
{"id": "J", "name": "Deployment", "duration": 2, "dependencies": ["I"]}
]
}
Analysis results: