delivery-risk-review【设计与创意】Identify, score, and mitigate delivery risks for a program or release. Use when the user says "risk review", "what could go wrong", "risk register", "delivery risks for this release", "program risk assessment", "identify blockers before they hit", or wants to pressure-test a plan before committing - even if they don't say "risk review". Based on "The…
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Based on "The Phoenix Project" (Kim, Behr & Spafford) and "The Art of Project Management" (Scott Berkun). The core insight from Phoenix Project: most delivery failures are not surprise events - they are predictable patterns (unplanned work, single points of failure, technical debt accumulation) that were visible before the crisis but ignored. A risk review forces you to name these patterns before they explode. Berkun adds: the highest-risk part of any project is not the work - it is the assumptions baked into the plan.
Ask the user for:
Work through five risk categories (drawn from Phoenix Project patterns and Berkun's scoping risk model):
Category 1: Unplanned Work Risk Questions to surface:
Phoenix Project signal: if unplanned work consumed > 20% of capacity in recent sprints, it will consume more during the release crunch.
Category 2: Dependency Risk Questions to surface:
Category 3: Scope Risk Questions to surface:
Berkun signal: any feature where the team has not done this type of work before carries a 2x estimation risk.
Category 4: People Risk Questions to surface:
Category 5: Technical Risk Questions to surface:
For each identified risk, assign:
| Impact Low | Impact Med | Impact High
-----------|------------|------------|------------
Likelihood High | P2 | P1 | P0
Likelihood Med | P3 | P2 | P1
Likelihood Low | P3 | P3 | P2
DELIVERY RISK REGISTER - [your program] - [date]
=================================================
P0 - ESCALATE NOW
| # | Risk | Category | Likelihood | Impact | Owner | Mitigation | Due |
|---|------|----------|-----------|--------|-------|------------|-----|
| 1 | [risk description] | [type] | High | High | [name] | [action] | [date] |
P1 - MONITOR WEEKLY
[same format]
P2/P3 - TRACK AND ACCEPT
[same format]
For each P0 and P1 risk, the mitigation must be one of:
"We'll keep an eye on it" is not a mitigation. Name the action, the owner, and the date.
Recommend a standing cadence based on program phase:
1. Identifying risks without owners Bad: "Technical debt in the auth service is a risk." Good: "[Name] will assess auth service test coverage by [date] and recommend if it needs a dedicated spike."
2. Only listing obvious risks Bad: Risk register with "API might be slow" and "team might be busy." Good: Surface non-obvious risks: knowledge concentration, unplanned work patterns, verbally-confirmed-but-not-written dependencies.
3. All risks rated the same Bad: 15 risks all rated "medium." Good: Force a distribution. If everything is medium, you have not done the analysis.
4. Risk review as a one-time event Bad: Risk register created at kickoff, never updated. Good: Risk register is a living document. Reviewed at program sync, statuses updated weekly.
5. Mitigation = monitoring Bad: "We will watch this closely." Good: A specific action that reduces likelihood or impact, with a named owner and due date.