manage-change-control【文档与办公】Manage change control for validated computerized systems. Covers change request triage (emergency, standard, minor), impact assessment on validated state, revalidation scope determination, approval workflows, implementation tracking, and post-change verification. Use when a validated system requires a software upgrade, patch, or configuration change;…
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Evaluate, approve, implement, and verify changes to validated computerized systems while maintaining their validated state.
# Change Request
## Document ID: CR-[SYS]-[YYYY]-[NNN]
### 1. Change Description
**Requestor:** [Name, Department]
**Date:** [YYYY-MM-DD]
**System:** [System name and version]
**Current State:** [Current configuration/version]
**Proposed State:** [Target configuration/version]
### 2. Justification
[Business, regulatory, or technical reason for the change]
### 3. Classification
| Type | Definition | Approval Path | Timeline |
|------|-----------|--------------|----------|
| **Emergency** | Urgent fix for safety, data integrity, or regulatory compliance | System owner + QA (retrospective CCB) | Implement immediately, document within 5 days |
| **Standard** | Planned change with potential impact on validated state | CCB approval before implementation | Per CCB schedule |
| **Minor** | Low-risk change with no impact on validated state | System owner approval | Documented before implementation |
**This change is classified as:** [Emergency / Standard / Minor]
**Rationale:** [Why this classification]
Expected: Change request has a unique ID, clear description, and justified classification. On failure: If classification is disputed, default to Standard and let the CCB adjudicate.
Evaluate the change against all dimensions of the validated state:
# Impact Assessment
## Change Request: CR-[SYS]-[YYYY]-[NNN]
### Impact Matrix
| Dimension | Affected? | Details | Risk |
|-----------|-----------|---------|------|
| Software configuration | Yes/No | [Specific parameters changing] | [H/M/L] |
| Source code | Yes/No | [Modules, functions, or scripts affected] | [H/M/L] |
| Database schema | Yes/No | [Tables, fields, constraints changing] | [H/M/L] |
| Infrastructure | Yes/No | [Servers, network, storage affected] | [H/M/L] |
| Interfaces | Yes/No | [Upstream/downstream system connections] | [H/M/L] |
| User access/roles | Yes/No | [Role changes, new access requirements] | [H/M/L] |
| SOPs/work instructions | Yes/No | [Procedures requiring update] | [H/M/L] |
| Training | Yes/No | [Users requiring retraining] | [H/M/L] |
| Data migration | Yes/No | [Data transformation or migration needed] | [H/M/L] |
| Audit trail | Yes/No | [Impact on audit trail continuity] | [H/M/L] |
### Regulatory Impact
- [ ] Change affects 21 CFR Part 11 controls
- [ ] Change affects EU Annex 11 controls
- [ ] Change affects data integrity (ALCOA+)
- [ ] Change requires regulatory notification
Expected: Every dimension is assessed with a clear yes/no and rationale. On failure: If impact cannot be determined without testing, classify the dimension as "Unknown — requires investigation" and mandate a sandbox evaluation before production change.
Based on the impact assessment, define what validation activities are needed:
# Revalidation Determination
| Revalidation Level | Criteria | Activities Required |
|--------------------|----------|-------------------|
| **Full revalidation** | Core functionality changed, new GAMP category, or major version upgrade | URS review, RA update, IQ, OQ, PQ, TM update, VSR |
| **Partial revalidation** | Specific functions affected, configuration changes | Targeted OQ for affected functions, TM update |
| **Documentation only** | No functional impact, administrative changes | Update validation documents, change log entry |
| **None** | No impact on validated state (e.g., cosmetic change) | Change log entry only |
### Determination for CR-[SYS]-[YYYY]-[NNN]
**Revalidation level:** [Full / Partial / Documentation only / None]
**Rationale:** [Specific reasoning based on impact assessment]
### Required Activities
| Activity | Owner | Deadline |
|----------|-------|----------|
| [e.g., Execute OQ test cases TC-OQ-015 through TC-OQ-022] | [Name] | [Date] |
| [e.g., Update traceability matrix for URS-007] | [Name] | [Date] |
| [e.g., Update SOP-LIMS-003 section 4.2] | [Name] | [Date] |
Expected: Revalidation scope is proportional to the change impact — no more, no less. On failure: If revalidation scope is contested, err on the side of more testing. Under-validation is a regulatory risk; over-validation is only a resource cost.
Route the change through the appropriate approval workflow:
# Change Approval
### Approval for: CR-[SYS]-[YYYY]-[NNN]
| Role | Name | Decision | Signature | Date |
|------|------|----------|-----------|------|
| System Owner | | Approve / Reject / Defer | | |
| QA Representative | | Approve / Reject / Defer | | |
| IT Representative | | Approve / Reject / Defer | | |
| Validation Lead | | Approve / Reject / Defer | | |
### Conditions (if any)
[Any conditions attached to the approval]
### Planned Implementation Window
- **Start:** [Date/Time]
- **End:** [Date/Time]
- **Rollback deadline:** [Point of no return]
Expected: All required approvers have signed before implementation begins (except emergency changes). On failure: For emergency changes, obtain verbal approval from system owner and QA, implement the change, and complete formal documentation within 5 business days.
Execute the change and perform post-change verification:
# Implementation Record
### Pre-Implementation
- [ ] Backup of current system state completed
- [ ] Rollback procedure documented and tested
- [ ] Affected users notified
- [ ] Test environment validated (if applicable)
### Implementation
- **Implemented by:** [Name]
- **Date/Time:** [YYYY-MM-DD HH:MM]
- **Steps performed:** [Detailed implementation steps]
- **Deviations from plan:** [None / Description]
### Post-Change Verification
| Verification | Result | Evidence |
|--------------|--------|----------|
| System accessible and functional | Pass/Fail | [Screenshot/log reference] |
| Changed functionality works as specified | Pass/Fail | [Test case reference] |
| Unchanged functionality unaffected (regression) | Pass/Fail | [Test case reference] |
| Audit trail continuity maintained | Pass/Fail | [Audit trail screenshot] |
| User access controls intact | Pass/Fail | [Access review reference] |
### Closure
- [ ] All verification activities completed successfully
- [ ] Validation documents updated per revalidation determination
- [ ] SOPs updated and effective
- [ ] Training completed for affected users
- [ ] Change record closed in change control system
Expected: Implementation matches the approved plan, and all verification activities pass. On failure: If verification fails, execute the rollback procedure immediately and document the failure as a deviation. Do not proceed without QA concurrence.
design-compliance-architecture — defines the governance framework including change control boardwrite-validation-documentation — create the revalidation documentation triggered by changesperform-csv-assessment — full CSV reassessment for major changes requiring full revalidationwrite-standard-operating-procedure — update SOPs affected by the changeinvestigate-capa-root-cause — when changes are triggered by CAPAs