create-work-breakdown-structure

create-work-breakdown-structure

【效率与协作】Create a Work Breakdown Structure (WBS) and WBS Dictionary from project charter deliverables. Covers hierarchical decomposition, WBS coding, effort estimation, dependency identification, and critical path candidates. Use after a project charter is approved, when planning a classic or waterfall project with defined deliverables, breaking a large initi…

独立 GitHub 快照 · 自动分类 · 以原作者文档为准

技能说明

GitHub

name: create-work-breakdown-structure locale: wenyan source_locale: en source_commit: 82c77053 fence_basis_commit: 82c77053 translator: "Julius Brussee homage — caveman" translation_date: "2026-04-19" description: > Create a Work Breakdown Structure (WBS) and WBS Dictionary from project charter deliverables. Covers hierarchical decomposition, WBS coding, effort estimation, dependency identification, and critical path candidates. Use after a project charter is approved, when planning a classic or waterfall project with defined deliverables, breaking a large initiative into manageable work packages, or establishing a basis for effort estimation and resource planning. license: MIT allowed-tools: Read Write Edit Bash Grep Glob metadata: author: Philipp Thoss version: "1.0" domain: project-management complexity: intermediate language: multi tags: project-management, wbs, work-breakdown-structure, classic, waterfall, planning

建工分結構

分項範為層級工包,可估、派、追。WBS 為估工、計資、定程之基,破繁交為可管之組件。

用時

  • 項章既准而範已定後
  • 劃有明交之古/瀑項
  • 破大舉為可管工包
  • 立估工與計資之基
  • 建諸所需工之共識

入

  • 必要:已准項章(尤範與交節)
  • 必要:項法(古/瀑,或劃用 WBS 之混)
  • 可選:似項之歷史工資
  • 可選:團組與可用技
  • 可選:組織之 WBS 樣或準

法

第一步:由章抽交

讀項章。列諸交與驗收。合為 3-7 頂類(此為 WBS 第一級之元)。

得: 合章之交之第一級 WBS 元列。

敗則: 若章泛,返 draft-project-charter 以精範。

第二步:分為工包

每第一級元,分為子元(第二、第三級)。施百分之百則:子必表父之全範。工包當:

  • 可估(可以人日派工)
  • 可派(一人或一團主之)
  • 可量(有清畢之準)

則止分。建 WBS 概:

# Work Breakdown Structure: [Project Name]
## Document ID: WBS-[PROJECT]-[YYYY]-[NNN]

### WBS Hierarchy

1. [Level 1: Deliverable Category A]
   1.1 [Level 2: Sub-deliverable]
      1.1.1 [Level 3: Work Package]
      1.1.2 [Level 3: Work Package]
   1.2 [Level 2: Sub-deliverable]
2. [Level 1: Deliverable Category B]
   2.1 [Level 2: Sub-deliverable]
3. [Level 1: Project Management]
   3.1 Planning
   3.2 Monitoring & Control
   3.3 Closure

施 WBS 碼(1.1.1 式)。至多 3-5 級深。皆含「Project Management」支。

得: 全 WBS 含 15-50 工包,每有唯一 WBS 碼。

敗則: 若分逾五級,範過大——考分為子項。

第三步:書 WBS 詞典

每工包(葉節)書詞典項:

# WBS Dictionary: [Project Name]
## Document ID: WBS-DICT-[PROJECT]-[YYYY]-[NNN]

### WBS 1.1.1: [Work Package Name]
- **Description**: What this work package produces
- **Acceptance Criteria**: How to verify it's done
- **Responsible**: Person or role
- **Estimated Effort**: [T-shirt size or person-days]
- **Dependencies**: WBS codes this depends on
- **Assumptions**: Key assumptions for this work package

### WBS 1.1.2: [Work Package Name]
...

得: 每葉工包有詞典項。

敗則: 缺詞典項示分不全——返第二步。

第四步:估工

每工包,施一估法:

  • T 恤尺(XS/S/M/L/XL)用於早期劃
  • 人日 用於詳劃
  • 三點估(樂觀/最可能/悲觀)用於高不確定工

建概表:

## Effort Summary
| WBS Code | Work Package | Estimate | Method | Confidence |
|----------|-------------|----------|--------|------------|
| 1.1.1 | [Name] | 5 pd | person-days | High |
| 1.1.2 | [Name] | M | t-shirt | Medium |

總工 = 諸工包之和。

得: 每工包有工估含信度。

敗則: 若 >30% 包信度低,與專家排精會。

第五步:識依與關鍵徑候選

映工包間依:

## Dependencies
| WBS Code | Depends On | Type | Notes |
|----------|-----------|------|-------|
| 1.2.1 | 1.1.1 | Finish-to-Start | Output of 1.1.1 is input to 1.2.1 |
| 2.1.1 | 1.1.2 | Finish-to-Start | |

識依包最長之鏈——此為關鍵徑候選。

得: 依表有至少識完始依。

敗則: 若依成環,分有誤——返第二步。

第六步:察而定基線

合 WBS 與詞典為終文。驗諸級百分之百則。獲相關者簽。

得: WBS.md 與 WBS-DICTIONARY.md 文件建而察。

敗則: 若相關者識缺範,加工包而重估。

驗

  • WBS 文件建含文件 ID 與 WBS 碼
  • 諸級皆滿百分之百則
  • 每葉節有 WBS 詞典項
  • 諸工包有工估
  • 依已識而無環
  • 含 Project Management 支
  • 關鍵徑候選已識
  • WBS 深不逾五級

陷

  • 混交與活:WBS 元當為名(交),非動(活)。「User Authentication Module」非「Implement Authentication」。
  • 違百分之百則:若子不合為父之全範,工將遺。
  • 過淺或過深:二級泛於劃;六級以上為微管。目標 3-5 級。
  • 略 PM 支:PM 工(劃、會、報)為實工費工。
  • 分前估:估工包非類。第一級之估不可靠。
  • 無詞典:無詞典之 WBS 為標之樹——詞典供畢之定。

參

  • draft-project-charter — 供範與交以饋 WBS 分
  • manage-backlog — 轉 WBS 工包為積項以追
  • generate-status-report — 依 WBS % 畢報進
  • plan-sprint — 若混法,由 WBS 工包劃衝
  • conduct-retrospective — 察估準與分質