generate-status-report【效率与协作】Generate a project status report by reading existing artifacts (charter, backlog, sprint plan, WBS), calculating metrics, identifying blockers, and summarizing progress with RAG indicators for schedule, scope, budget, and quality. Use at the end of a sprint or reporting period, when stakeholders request a health update, before steering committee or g…
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Make periodic status report. Analyze project artifacts, compute progress metrics, summarize accomplishments, blockers, upcoming work with RAG (Red/Amber/Green) health indicators.
Scan project directory for PM artifacts:
Read available files. Not all will exist — adapt report to available data.
Got: At least one artifact read successful, key metrics extracted.
If fail: No artifacts exist? Report can't be generated. Create charter or backlog first with draft-project-charter or manage-backlog.
Compute metrics from available data:
Agile metrics (from BACKLOG.md / SPRINT-PLAN.md):
Classic metrics (from WBS.md):
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
Got: 3-5 metrics computed with previous period comparison.
If fail: No historical data (first report)? Skip Previous + Trend columns. Data incomplete → note gaps in report footer with actions to establish tracking.
List active blockers + risks:
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
Cross-reference vs charter risk register. Flag new risks not previously identified.
Got: All active blockers + top risks documented with owners + actions.
If fail: No blockers? State "No active blockers" — no empty section. Blocker without owner? Escalate to project manager.
Write two sections:
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
Got: 3-5 accomplishments with concrete evidence, 3-5 planned items for next period.
If fail: No accomplishments? Report reason (blocked, re-planning, team unavailable). Next period plan unclear → list "Planning session scheduled for [date]" as primary.
Assess project health across four dimensions:
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
Write complete report:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
Save as STATUS-REPORT-[YYYY-MM-DD].md.
Got: Complete status report saved with RAG indicators, metrics, narrative.
If fail: Data insufficient for RAG assessment? Use ⚪ (Grey) = "insufficient data", list what data needs collecting for next report.
draft-project-charter — charter provides milestones + success criteria for status trackingmanage-backlog — backlog metrics feed status reportplan-sprint — sprint results provide velocity + completion datacreate-work-breakdown-structure — WBS completion drives classic progress metricsconduct-retrospective — status report data feeds retrospective