【开发与工程】Score a subcontractor's performance across schedule reliability, quality, safety, paperwork, and change-order behaviour with weighted anchors. Use when asked to evaluate a sub, build a subcontractor scorecard, decide whether to rebid or rehire a trade, review sub performance for prequalification, or justify removing a sub from the bid list. Produces …

独立 GitHub 快照 · 自动分类 · 以原作者文档为准

技能说明

GitHub

name: subcontractor-scorecard description: "Score a subcontractor's performance across schedule reliability, quality, safety, paperwork, and change-order behaviour with weighted anchors. Use when asked to evaluate a sub, build a subcontractor scorecard, decide whether to rebid or rehire a trade, review sub performance for prequalification, or justify removing a sub from the bid list. Produces a weighted scorecard with per-dimension anchored ratings, evidence notes, and an award/retention recommendation."

Subcontractor Scorecard Skill

Every GC has a mental list of subs they'd hire again and subs they'd rather eat the higher bid to avoid. This skill turns that instinct into a defensible record: five weighted dimensions, anchored 1–5 scales so two reviewers score alike, evidence per rating, and a recommendation you can put in front of a preconstruction meeting — or a sub's principal — without it reading as a grudge.

What This Skill Produces

  • A weighted scorecard across five dimensions with a 0–100 composite score
  • Anchored 1–5 ratings per dimension with the evidence behind each
  • A recommendation tier: preferred / approved / conditional / do-not-rebid
  • Feedback points suitable for a performance conversation with the sub
  • Optional side-by-side comparison when scoring multiple subs in a trade

Required Inputs

Ask for what's missing; from partial data, score what's evidenced and mark unscored dimensions [insufficient data] rather than guessing:

  • Sub and trade, projects covered by the evaluation, contract values
  • Schedule facts — milestones hit/missed, manpower vs. commitments, recovery behaviour
  • Quality facts — punch item counts vs. trade norms, rework/back-charges, inspection failures, submittal quality
  • Safety facts — recordables/near-misses on your sites, EMR if known, toolbox/permit compliance
  • Paperwork facts — timeliness of lien waivers, certified payroll, insurance certs, closeout docs
  • Change-order behaviour — pricing reasonableness, claims posture, T&M ticket discipline

Scoring Framework

Score each dimension 1–5 against the anchors, then weight:

DimensionWeight1 (fails)3 (solid)5 (excellent)
Schedule reliability30%Chronic slips, ghost crews, drives the critical path lateHits most dates; slips flagged early with recovery planHits dates, staffs to plan, accelerates when asked without drama
Quality / rework25%Repeated failed inspections, punch counts far above trade norm, back-charged reworkNormal punch volume, closes items promptly, rare reworkFirst-time-quality culture; punch list light and closed fast
Safety20%Recordable(s) from ignored controls; fights the safety programCompliant; participates in briefings; near-misses reportedBrings hazards to you first; crews self-police; clean record
Paperwork discipline10%Chases required for waivers/certs; closeout drags monthsMostly on time with remindersBilling, waivers, and closeout docs arrive right, first time
Change-order behaviour15%Weaponises COs — lowball bid, then claims on every RFIPrices changes fairly with backup; negotiates in good faithFlags cost issues before they're changes; transparent pricing

Composite = Σ(rating × weight) × 20, giving 0–100. Map to a recommendation:

  • 85–100 Preferred — invite to negotiate, consider for design-assist
  • 70–84 Approved — keep on the bid list
  • 55–69 Conditional — rebid with specific conditions (named super, weekly look-ahead, tighter retainage)
  • <55 Do-not-rebid — document why; a low bid from this sub isn't a low cost

Safety scores of 1–2 cap the overall recommendation at Conditional regardless of composite — a sub who hurts people isn't "preferred" at any price.

Output Format

Subcontractor Scorecard: [Sub] — [Trade] — [Period/projects]

1. Composite score & recommendation tier — with the one-paragraph justification. 2. Dimension table — | Dimension | Weight | Rating (1–5) | Evidence | 3. Trend note — improving, stable, or declining vs. prior projects, if history given. 4. Conditions / feedback points — specific, evidence-backed items for the sub conversation. 5. Data gaps — dimensions scored on thin evidence, flagged [insufficient data].

Quality Checks

  • Every rating cites specific evidence (project, event, count) — no vibes-only scores
  • Weights sum to 100% and the composite math is shown
  • Safety cap rule applied if safety scored 1–2
  • Recommendation tier follows from the score — or the override is stated and justified
  • Feedback points are usable in a face-to-face with the sub's principal without escalating

Anti-Patterns

  • Do not let one bad final month erase a good project — score the whole evaluation period
  • Do not score paperwork as highly as schedule — the weights exist because the failure modes aren't equal
  • Do not average away a safety failure inside the composite — apply the cap rule
  • Do not write "poor attitude" as evidence — describe the behaviour and its project impact
  • Do not score dimensions you have no data for — mark [insufficient data] and say what record-keeping would fix it

Example Trigger Phrases

  • "Evaluate a sub."
  • "Build a subcontractor scorecard."
  • "Decide whether to rebid."
  • "Rehire a trade."
  • "Review sub performance for prequalification."