action-priority-ap【文档与办公】Assign AP table ratings (H-AP, M-AP, L-AP) in PFMEA or DFMEA — the RPN replacement from AIAG-VDA FMEA Handbook 2019. Explains H/M/L classification logic, mandatory action requirements for High Priority items, and OEM-specific thresholds. Use when assigning risk levels in PFMEA or DFMEA, or auditing FMEA documents for AP compliance.
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Assign and audit Action Priority (AP) ratings correctly using the AIAG-VDA 2019 method, ensuring high-risk items receive justified action or formal risk acceptance. This skill is used when classifying risk levels in PFMEA or DFMEA, reviewing existing ratings, or auditing FMEA documents for AP compliance.
☐ Confirm the linked Failure Effect, Failure Mode, and Failure Cause are correct before assigning AP ☐ Confirm S is based on the Failure Effect (severity to the customer or end user) ☐ Confirm O is based on the Failure Cause with current prevention controls in place ☐ Confirm D is based on current detection controls for this Failure Mode ☐ All S, O, and D ratings are supported by data, field history, capability data, or documented engineering judgement — not guesses ☐ Assign AP using the full AP determination rules (see ap-table.md) — not only the summary patterns in this skill ☐ For formal PPAP submissions, customer-facing FMEAs, or any disputed rating, confirm against your licensed AIAG-VDA FMEA Handbook — the rating criteria that make an S, O or D value defensible are in the handbook, not in this skill ☐ For every H-AP item: define a corrective action with owner and target date, or document a formal escalation rationale ☐ Reassess AP only after the corrective action is implemented and verified — not when only planned ☐ Verify Special Characteristics are rated S = 9 or 10 ☐ Document the evaluation decision for every M-AP item (action taken or rationale for no action) ☐ Document rationale for every L-AP item
The legacy RPN = Severity × Occurrence × Detection had critical flaws:
Problem 1 — Same RPN, very different risk
Problem 2 — Easy to game Teams learned to lower RPN cheaply by improving detection (adding an inspection step). D: 8→3 drops RPN by 62.5%. But the defect is still being made — it's just being caught later. Prevention (reducing occurrence) is harder but far more valuable.
Problem 3 — No mandatory threshold RPN had no defined threshold for mandatory action. "High RPN" meant different things to different teams and customers.
The AP fix:
Action required. Assign a responsible person and a target completion date.
If no improvement is achievable (technically or economically), the team must:
H-AP items must never be silently ignored.
Conditions that always produce H:
Action recommended. The team should evaluate whether risk reduction is beneficial.
M-AP does not mean "no action needed." It means action is not mandatory, but the team must document its evaluation decision:
No action required. Document rationale for the record.
This skill explains AP logic and decision patterns. Use the full AP determination rules (ap-table.md) for final rating assignment. Do not rely solely on the summary patterns below for disputed cases or formal PPAP submissions — those require the rating criteria in your licensed AIAG-VDA FMEA Handbook.
Before assigning AP: Do not assign AP unless S, O, and D are already justified based on the linked failure effect, failure cause, and current controls. AP is only as good as the ratings it is built on.
For each FC (Failure Cause) row in the PFMEA/DFMEA:
1. Assign S (for the linked Failure Effect)
2. Is S = 9 or 10?
→ Yes: AP = H. Done.
→ No: continue
3. Assign O (for this Failure Cause with current prevention controls)
4. Assign D (for this Failure Mode with current detection controls)
5. Look up AP in the full table (see ../pfmea-process/assets/ap-table.md)
All S, O, and D ratings must be supported by test data, field history, capability data, or documented engineering judgement.
The patterns below are practical summaries for working use. Final AP assignment must always be confirmed against the full AIAG-VDA AP table. For disputed cases or audits, the full table takes precedence.
| O | D | AP |
|---|---|---|
| Any | Any | H |
| O | D | AP |
|---|---|---|
| 6–10 | Any | H |
| 4–5 | 6–10 | H |
| 4–5 | 1–5 | M |
| 1–3 | Any | M |
| O | D | AP |
|---|---|---|
| 6–10 | 7–10 | H |
| 6–10 | 4–6 | M |
| 6–10 | 1–3 | M |
| 4–5 | 7–10 | M |
| 4–5 | 4–6 | M |
| 4–5 | 1–3 | L |
| 1–3 | Any | L |
| O | D | AP |
|---|---|---|
| 8–10 | 7–10 | H |
| 8–10 | 4–6 | M |
| 8–10 | 1–3 | M |
| 5–7 | 7–10 | M |
| 5–7 | 1–6 | L |
| 1–4 | Any | L |
All combinations → L
Do not lower AP based on planned actions. Revised AP may only be assigned after the corrective action is implemented and the implementation is verified with objective evidence. A planned action is not a completed action.
Audit questions:
| OEM | AP requirement |
|---|---|
| Ford | H-AP items require mandatory action or documented engineering justification (EJ) |
| GM | BIQS requires all H-AP items closed before PPAP Level 3 |
| VW/Audi | AP H must be actioned or formally accepted by responsible engineer |
| BMW | AP H items listed on open issues list until closed |
| Stellantis | H-AP items require SQE approval for acceptance without action |
Customer-Specific Requirements (CSR) are revision-controlled and may change. Always verify the latest customer requirement before release, PPAP, or customer submission. See oem-requirements.md for OEM-specific detail.
At the start of each use, ask the user:
"How would you like to receive the output? A — Structured Markdown (formatted tables and sections, ready to copy) B — Plain tables (simplified structure for Excel or Word) C — Narrative report (flowing text for a formal document or email)
Default: A."
Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.
| Version | Date | Author | Change |
|---|---|---|---|
| 1.0 | 2026-06-01 | @RBraga01 | Initial release |
| 1.1 | 2026-06-03 | @migmcc | Polished AP classification logic, added OEM CSR requirements table |