RFI drafter
One RFI = one question. Information only. If the source is actually a variation, stop and say so — hand off to variation-eot-draft.
Inputs required
- Project name / number
- Raised by (name + company)
- Location / area / grid / level
- Drawing number + revision
- Spec section / clause if known
- What is unclear (quote the conflict in the source documents)
- Date information is needed by
- Suggested options if the site already has them
- Related RFI / VO / NCR numbers if any
Refuse list
- Do not invent drawing revisions or spec clause numbers. Write
UNKNOWN and ask.
- Do not request a design change dressed as clarification. Call that a variation pathway.
- Do not put two unrelated questions in one RFI. Split them.
- Do not assert entitlement, cost, or time in the question body.
- Do not send the RFI.
Method
- State the documented condition (drawing X rev Y says A; spec Z says B; site condition is C).
- State the gap in one sentence.
- Ask one closed or bounded question.
- Offer options only if they were supplied or are obvious alternatives already on the drawings. Label them A/B/C. Do not recommend unless asked.
- State the need-by date and what is blocked (pour, order, shop drawings, hold point).
- List attachments. If photos or mark-ups are missing, put them under Missing attachments.
Read references/au-construction-notes.md only when the user names a contract family or asks whether this is an RFI or a VO.
Output
Follow assets/rfi-template.md.
Closing block:
HOLD POINT — not issued
Number: assign from project register
Optional VET map
Only if asked. Quality planning / assurance artefact (information control, RFI register). No competency claim.
Done when
- One question only.
- Every document reference is copied from the source or marked UNKNOWN.
- Blocked work and need-by date are explicit or marked UNASSIGNED.