计划执行与检查节点
executing-plans
按既定实施计划完成工作,保持过程检查和反馈。
fast-workflow【效率与协作】Use when planning a USENIX FAST project timeline from venue fit through choosing a Spring or Fall deadline, double-blind submission, the author-response period, shepherding or a one-shot revision, artifact evaluation, and the open-access camera-ready, with backward-planning offsets tuned to storage evaluation and honest handling of the two-deadline c…
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Use this as the project-management skill for a FAST submission. Replace every date with the current official timetable and work backwards from the deadline you choose. FAST — the USENIX Conference on File and Storage Technologies — runs two deadlines a year, has an author-response period, and can issue a one-shot revision that spans into the next deadline, so plan for a longer arc than a plain accept/reject conference.
FAST is a USENIX conference: it has no standing editor-in-chief and no article-processing charge. Rotating leadership is the per-edition Program Co-Chairs and the program committee, and the cost model is registration plus USENIX membership — proceedings are open access. Chairs and the Artifact Evaluation Committee rotate yearly; re-check the current committee page rather than carrying a name forward (FAST '27 rosters: 待核实 beyond what the CFP names).
FAST '27 offers Spring (submit 17 Mar 2026, notify 4 Jun 2026, final files 28 Jul 2026) and Fall (submit 15 Sep 2026, notify 8 Dec 2026, final files 26 Jan 2027). Pick by evidence readiness — storage measurements at steady state on real, aged devices take real calendar time — not by whichever is nearest. As of 2026-07-09 the Spring round is notified and the live target is the Fall deadline, 15 Sep 2026.
fast-topic-selection).| Weeks out (heuristic) | Storage-evaluation milestone |
|---|---|
| 12+ | Testbed fixed: device models/firmware, kernel, mkfs options; workloads/traces chosen |
| 10 | Device-state protocol locked (aging/preconditioning, fill level, TRIM); baselines built and tuned |
| 8 | Measurement runs complete at steady state; device counters (SMART/logs) captured; provenance logged |
| 6 | Analysis done; tail-latency distributions, write-amplification, endurance projections computed |
| 4 | Full draft in the USENIX template; artifact + trace-replay scripts assembled and anonymized |
| 3 | Internal mock review by a storage reader |
| 2 | Caveats hardened, related-work delta sharpened, page limit met |
| 1 | Double-blind sweep on PDF and artifact; availability statement final |
| 0 | Register the abstract on the correct HotCRP, then upload |
These offsets are planning heuristics only — anchor every one to the current Important Dates block, never to a previous cycle's calendar. Note that storage runs (aging a drive, replaying a long trace, an endurance test) can dominate the schedule; size them explicitly.
[Current stage] idea / evidence / writing / registration / submitted / response / shepherd-or-revision / accepted
[Target deadline] Spring / Fall <date and source, or unknown>
[Critical path] <three tasks that determine readiness — often measurement-time-bound>
[Risk register] <page limit / anonymity / device state / provenance / tail latency / artifact>
[Owner map] <task -> person or role>