colt-workflow【效率与协作】Use when planning a COLT (Conference on Learning Theory) submission calendar backward from the single AoE paper deadline — proof-completion and verification milestones, writing and appendix-assembly passes, CMT logistics, the rebuttal window, decision aftermath, and PMLR camera-ready with conference presentation in early summer.
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Use this as the project-management layer for a COLT paper. Anchor everything to the live timetable: for the 39th edition the CFP (checked 2026-07-08) set one submission deadline — February 4, 2026, Anywhere on Earth, via CMT — for a conference running June 29 to July 3, 2026 in San Diego. Notification and camera-ready dates were not on the checked pages (待核实); take them from the CFP and acceptance email of your cycle.
colt-topic-selection); if the result is 80% proved, the clock question is
whether the remaining 20% is verification or invention — only the first is
schedulable.colt-reproducibility). Schedule it as real work with an owner per theorem — it
finds bugs at a rate authors never want to believe.colt-submission).colt-author-response).colt-camera-ready);
rejection → triage between fix-and-resubmit (next COLT / ALT) and re-routing.| Weeks before deadline | Milestone | Failure smell |
|---|---|---|
| 10+ | All main results proved at whiteboard level | "The lower bound should follow" — it does not, yet |
| 8 | Theorem statements frozen; ledger of claims opened | Statements still absorbing scope changes |
| 6 | Full proofs written in LaTeX, appendix-structured | Proofs alive only in notebooks and heads |
| 4 | Independent verification pass complete; bugs triaged | "We'll verify while writing" (you will not) |
| 3 | Body drafted: setup, results, proof overviews, known-vs-new table | Overview promises diverging from actual proofs |
| 2 | Internal mock review by an uninvolved theorist | No one external has read the model section |
| 1 | Anonymity sweep, notation audit, cross-reference check | Renumbering theorems this late |
| 0 | Upload, re-download, verify the stored PDF; stop editing | Compiling at the AoE boundary |
Weeks are heuristics; the deadline is not. AoE means when it is February 4 anywhere on Earth — compute your local cutoff and subtract a safety day.
For a theory paper the long pole is never the writing; it is discovering at week 2 that Lemma 6 is false. Mitigations:
colt-artifact-evaluation) as the single source of
verification status; standups read the ledger, not vibes.# colt-plan.txt
DEADLINE (AoE): 2026-02-04 -> local cutoff 2026-02-05 11:59 UTC-12
RESULT FREEZE: 2025-12-10 owner: all
PROOF APPENDIX DRAFT: 2025-12-22 owner: A (Thm 1), B (Thm 2, lower bound)
VERIFICATION PASS: 2026-01-09 owner: swap (B checks Thm 1, A checks Thm 2)
BODY + OVERVIEWS: 2026-01-16 owner: A
MOCK REVIEW: 2026-01-21 reader: C (not a coauthor)
ANONYMITY + PDF QA: 2026-01-28 owner: B
UPLOAD TARGET: 2026-02-02 (two days of slack, CMT record made 01-25)
REBUTTAL WINDOW: dates TBA with reviews -> block capacity on release
[Stage] proving / freeze / verification / writing / submitted / rebuttal / decision
[Critical path] <the unverified claim or unwritten proof gating everything>
[Calendar] <next official date + source, or 待核实>
[Owner map] <theorem/task -> person>
[Slack] <days between planned upload and AoE cutoff>