emnlp-workflow【开发与工程】Use when planning an EMNLP project calendar end to end — choosing the ACL Rolling Review cycle that feeds the conference, backward-planning experiments and annotation to the ARR deadline, scheduling the author response window, deciding commit versus revise-and-resubmit, and mapping camera-ready and Budapest presentation logistics.
独立 GitHub 快照 · 自动分类 · 以原作者文档为准
Use this as the project-management skill for an EMNLP paper. The defining fact: EMNLP has no direct paper deadline of its own. The clock that matters is the ARR cycle aligned with the conference, and missing it usually means committing from an earlier cycle or waiting for the next conference. All dates below are the 2026 configuration (checked 2026-07-08); re-anchor every one against the live calendar.
| Date (2026) | Event | Owner |
|---|---|---|
| May 25 | ARR May cycle submission deadline | ARR |
| May 27 | Author registration form (EoD AoE) | ARR |
| Jul 6 | Reviews due from reviewers | ARR |
| Jul 7-13 | Author response + author-reviewer discussion | ARR |
| Jul 30 | Meta-reviews released | ARR |
| Aug 2 | Commitment deadline for EMNLP | Conference |
| Aug 20 | Acceptance notification (Main / Findings / reject) | Conference |
| Sep 20 | Camera-ready | Conference |
| Oct 24-29 | EMNLP 2026, Budapest (hybrid) | Conference |
Parallel option: the Industry Track took direct OpenReview submissions until June 16,
2026 — a genuinely different pipeline (see emnlp-topic-selection for routing).
NLP papers die on data and annotation lead times more often than on modeling. Working back from a late-May deadline:
Between meta-review (Jul 30) and commitment (Aug 2) sits a real strategic choice with a 72-hour fuse in 2026:
Draft the commit/revise decision tree before July 30. Three days is enough to execute a decision, not to have the argument.
Role map for a 4-author EMNLP submission
- Evidence owner: experiment grid, seeds, significance tests, error analysis
- Data owner: licenses, contamination checks, annotation pipeline, agreement stats
- Compliance owner: template, checklist, anonymization, citation resolution
- Response owner: drafts the July response, tracks each reviewer thread
(One person may hold two roles; no role may have zero owners.)
Archive the exact submitted PDF and checklist on deadline day — the July response must quote them precisely, and the camera-ready diff will be audited against them.
Because ARR runs continuously, missing the aligned cycle is a detour, not a year lost — but the detour has geometry worth knowing in advance:
Plan for the fact that three distinct clocks tick in the same week: the paper PDF (May 25), the author registration form (May 27), and any reciprocal-reviewing qualification data the form demands. In the May 2026 cycle the reviewer pool ran at roughly one AC per twelve submissions, and ARR expanded reciprocal assignments to cope — meaning a multi-paper group could owe several reviews landing in June, exactly when the group planned to rest. Put the reviewing obligation on the same calendar as the submission, with a named owner per obligated author.
[Current phase] scoping / data / experiments / writing / submitted / response / commitment / accepted
[Next hard deadline] <date + owner (ARR vs conference) + source URL>
[Critical path] <three tasks gating the next deadline>
[Commitment posture] commit / revise-resubmit / undecided — with rationale
[Role gaps] <unowned roles from the role map>