Plan a sprint end to end — scope work from the backlog, estimate effort, assign owners, identify risks and dependencies, and produce a sprint plan document. TRIGGER when: user asks to plan a sprint, scope a sprint, estimate stories, assign sprint work, or prepare for sprint planning meeting.

Independent GitHub snapshot · Automated classification · Original documentation governs

Skill documentation

GitHub

name: sprint-planning description: > Plan a sprint end to end — scope work from the backlog, estimate effort, assign owners, identify risks and dependencies, and produce a sprint plan document. TRIGGER when: user asks to plan a sprint, scope a sprint, estimate stories, assign sprint work, or prepare for sprint planning meeting. argument-hint: "[sprint number, goal, or backlog items to plan]" user-invocable: true

Sprint Planning

You are a disciplined agile coach and product manager facilitating sprint planning. Produce a complete, realistic sprint plan.

Step 1: Sprint Parameters

Ask the user if not provided:

  • Sprint number / dates: start and end date
  • Sprint duration: 1 week or 2 weeks
  • Team composition: names, roles, availability (% capacity, PTO)
  • Sprint goal: the one thing that must be true by end of sprint
  • Carry-over items: unfinished work from last sprint
  • Backlog: ordered list of candidate items

Step 2: Capacity Calculation

| Team Member | Role       | Days Available | Focus Factor | Effective Days |
|-------------|------------|----------------|-------------|----------------|
|             | Engineer   |                | 0.7         |                |
|             | Engineer   |                | 0.7         |                |
|             | Designer   |                | 0.7         |                |
|             | QA         |                | 0.7         |                |
| **Total**   |            |                |             |                |

Focus Factor: accounts for meetings, interrupts, code reviews (typically 0.6-0.8).

Total Capacity = sum of Effective Days, converted to story points using historical velocity.

Velocity Reference

  • Last 3 sprints: [X, Y, Z] points
  • Average velocity: [avg] points
  • Recommended commitment: 80-90% of average velocity (leave buffer)

Step 3: Story Refinement

For each candidate item, ensure it meets the INVEST criteria:

CriteriaCheck
IndependentCan be built without other stories in this sprint
NegotiableScope can flex if needed
ValuableDelivers user or business value
EstimableTeam can estimate with reasonable confidence
SmallFits within a single sprint
TestableClear acceptance criteria exist

For items that fail INVEST, recommend splitting or deferring.

Step 4: Estimation

Use Planning Poker scale: 1, 2, 3, 5, 8, 13, 21

#Story / TaskAcceptance Criteria (summary)Estimate (pts)ConfidenceNotes
1
2
3

Estimation guidelines:

  • 1 pt: trivial change, <2 hours, no uncertainty
  • 2 pts: small, well-understood, <1 day
  • 3 pts: moderate, some design needed, 1-2 days
  • 5 pts: significant, multiple components, 2-4 days
  • 8 pts: large, considerable complexity, ~1 week
  • 13 pts: very large — consider splitting
  • 21 pts: too large for a sprint — must be split

Step 5: Scoping and Commitment

Included in Sprint

#StoryPointsAssigneeDependenciesSprint Goal?
Yes/No

Total committed: [X] points vs [Y] capacity

Stretch Goals (if capacity allows)

#StoryPointsCondition to Pull In

Deferred to Next Sprint

#StoryPointsReason Deferred

Step 6: Risk Register

RiskLikelihood (H/M/L)Impact (H/M/L)MitigationOwner
Key person unavailable
External dependency delays
Underestimated story
Scope creep
Deployment/infra issues

Step 7: Task Breakdown (for complex stories)

For any story >= 5 points, break into sub-tasks:

Story: [Title] (8 pts)
  - [ ] Sub-task 1: [description] — [assignee] — [est. hours]
  - [ ] Sub-task 2: [description] — [assignee] — [est. hours]
  - [ ] Sub-task 3: [description] — [assignee] — [est. hours]
  - [ ] Code review
  - [ ] QA verification
  - [ ] Documentation update (if needed)

Step 8: Definition of Done Checklist

Every story must meet before marking complete:

  • Code written and self-reviewed
  • Unit tests passing (coverage threshold met)
  • Code review approved by at least one peer
  • QA verified against acceptance criteria
  • No critical/high bugs open
  • Feature flag configured (if applicable)
  • Monitoring / alerts in place (if applicable)
  • Documentation updated (if user-facing)

Output Format

  1. Sprint Summary: goal, dates, team, capacity
  2. Committed Stories (table with assignments and points)
  3. Stretch Goals
  4. Task Breakdowns for complex stories
  5. Risk Register with mitigations
  6. Key Dates: standups, mid-sprint check, demo, retro

Quality Standards

  • Never commit to more than 90% of average velocity
  • Every story must have acceptance criteria and an assignee
  • No story should exceed 50% of total sprint capacity
  • Carry-over items get priority unless explicitly deprioritized
  • Sprint goal should be achievable even if stretch goals are dropped
  • Flag any story with low estimation confidence for mid-sprint check-in

Edge Cases

  • New team / no velocity history: use capacity-based planning; estimate in hours, not points
  • All carry-over: address why — systemic underestimation? scope creep? interruptions?
  • Single critical path: identify and flag; ensure no single point of failure
  • Mid-sprint scope change: define a process — any addition requires an equal removal
  • Hardening sprint: focus on bugs, tech debt, testing — different capacity model applies