L’interface est localisée ; les présentations et documents des Skills sont traduits automatiquement par IA dans votre langue. Le code, les commandes, chemins et termes techniques restent en version originale, et le document de l’auteur fait foi.
Explorer les Skills
Documents · SKILL.md

sprint-plan

sprint-plan

Generates a new sprint plan or updates an existing one based on the current milestone, completed work, and available capacity. Pulls context from production documents and design backlogs.

Independent GitHub snapshot · Automated classification · Original documentation governs

Documentation de la Skill

GitHub

name: sprint-plan description: "Generates a new sprint plan or updates an existing one based on the current milestone, completed work, and available capacity. Pulls context from production documents and design backlogs." argument-hint: "[new|update|status]" user-invocable: true allowed-tools: Read, Glob, Grep, Write, Edit context: | !ls production/sprints/ 2>/dev/null

When this skill is invoked:

  1. Read the current milestone from production/milestones/.

  2. Read the previous sprint (if any) from production/sprints/ to understand velocity and carryover.

  3. Scan design documents in design/gdd/ for features tagged as ready for implementation.

  4. Check the risk register at production/risk-register/.

For new:

  1. Generate a sprint plan following this format:
# Sprint [N] -- [Start Date] to [End Date]

## Sprint Goal
[One sentence describing what this sprint achieves toward the milestone]

## Capacity
- Total days: [X]
- Buffer (20%): [Y days reserved for unplanned work]
- Available: [Z days]

## Tasks

### Must Have (Critical Path)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Should Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Nice to Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

## Carryover from Previous Sprint
| Task | Reason | New Estimate |
|------|--------|-------------|

## Risks
| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|

## Dependencies on External Factors
- [List any external dependencies]

## Definition of Done for this Sprint
- [ ] All Must Have tasks completed
- [ ] All tasks pass acceptance criteria
- [ ] No S1 or S2 bugs in delivered features
- [ ] Design documents updated for any deviations
- [ ] Code reviewed and merged

For status:

  1. Generate a status report:
# Sprint [N] Status -- [Date]

## Progress: [X/Y tasks complete] ([Z%])

### Completed
| Task | Completed By | Notes |
|------|-------------|-------|

### In Progress
| Task | Owner | % Done | Blockers |
|------|-------|--------|----------|

### Not Started
| Task | Owner | At Risk? | Notes |
|------|-------|----------|-------|

### Blocked
| Task | Blocker | Owner of Blocker | ETA |
|------|---------|-----------------|-----|

## Burndown Assessment
[On track / Behind / Ahead]
[If behind: What is being cut or deferred]

## Emerging Risks
- [Any new risks identified this sprint]

Agent Consultation

For comprehensive sprint planning, consider consulting:

  • producer agent for capacity planning, risk assessment, and cross-department coordination
  • game-designer agent for feature prioritization and design readiness assessment
Skills enregistrées