draft-project-charterDraft a project charter that defines scope, stakeholders, success criteria, and initial risk register. Covers problem statement, RACI matrix, milestone planning, and scope boundaries for both agile and classic methodologies. Use when kicking off a new project or initiative, formalizing scope after an informal start, aligning stakeholders before detailed pla…
Independent GitHub snapshot · Automated classification · Original documentation governs
立範圍、相關者、成敗、風險。
讀舊文。識核心問題。建章程文件。
建 PROJECT-CHARTER-[PROJECT-NAME].md:
# Project Charter: [Project Name]
## Document ID: PC-[PROJECT]-[YYYY]-[NNN]
### 1. Problem Statement
[2-3 sentences describing the problem or opportunity this project addresses]
### 2. Project Purpose
[What the project will achieve and why it matters]
### 3. Scope
#### In Scope
- [Deliverable 1]
- [Deliverable 2]
#### Out of Scope
- [Exclusion 1]
- [Exclusion 2]
### 4. Deliverables
| # | Deliverable | Acceptance Criteria | Target Date |
|---|------------|---------------------|-------------|
| 1 | | | |
### 5. Stakeholders & RACI
| Stakeholder | Role | D1 | D2 | D3 |
|-------------|------|----|----|-----|
| | | | | |
*R=Responsible, A=Accountable, C=Consulted, I=Informed*
### 6. Success Criteria
| # | Criterion | Measure | Target |
|---|-----------|---------|--------|
| 1 | | | |
### 7. Milestones
| Milestone | Target Date | Dependencies |
|-----------|-------------|--------------|
| | | |
### 8. Risk Register
| ID | Risk | Likelihood | Impact | Severity | Mitigation | Owner |
|----|------|------------|--------|----------|------------|-------|
| R1 | | | | | | |
*Likelihood/Impact: Low, Medium, High*
*Severity = Likelihood × Impact*
### 9. Assumptions and Constraints
#### Assumptions
- [Key assumption 1]
#### Constraints
- [Key constraint 1]
### 10. Approval
| Role | Name | Date |
|------|------|------|
| Sponsor | | |
| Project Lead | | |
填 ID:PC-[PROJECT]-[YYYY]-[NNN]。問題陳述 2-3 句:現況、缺口、影響。目的 1 段。
得: 文件成,ID、問題、目的齊。問題具體可量。
敗: 脈絡不明→於頭置 QUESTIONS 段錄問。文件矛盾→記 OPEN ISSUES。
列入範與出範。入範交付物 3-5,各具驗收標準。出範 3-5 防蔓延。填交付表。
得: 入出平衡。表 3-5 項,標準可驗。日期合理有序。
敗: 模糊→拆子項。標準缺→問「何以證畢?」。日期無→標 TBD。
列受影響、貢獻、決策者。含組織角色。建 RACI 矩陣:
每交付物:恰一 A,至少一 R。
得: 表列 5-10 人。各列一 A。無缺 R、無多 A。發起人為終批之 A。
敗: 名單缺→對組織圖+探索期會議。多 A→上報發起人。無 R→標未派,須資源。
3-5 SMART 標準:具體、可量、可達、相關、有期。各繫量值+目標。4-6 里程碑,有日期+依賴。
得: 表 3-5 項,量具體(如「系統在線」量為「%可用」目標「99.5%」)。里程碑合理有序,依賴明。
敗: 模糊(「提升質」)→重寫可量。日期不實→由終期反推+緩衝。循環依賴→重序或拆分。
5-10 風險。各評可能(低/中/高)+影響(低/中/高)→嚴重度。定具體緩解+派所有者。至少各一:範圍、進度、資源、技術、外部。
得: 5-10 項涵五類。各具可能、影響、嚴重度。緩解可行具體。各有主。
敗: 缺→察範圍、依賴、相關者、假設尋失敗點。緩解泛(「密切監控」)→問「何→監?幾何時→監?何觸發?」。無人認領→暫派項目主,上報發起人。