plan-release-cyclePlan a software release cycle with milestones, feature freezes, release candidates, and go/no-go criteria. Covers calendar-based and feature-based release strategies. Use when starting planning for a major or minor version release, transitioning from ad-hoc to structured release cadence, coordinating a release across multiple teams or components, defining q…
Independent GitHub snapshot · Automated classification · Original documentation governs
為軟體發布規劃結構化週期:定策略(依曆或依功能)、設里程碑與目標日、立功能凍結準則、管理候選版本、定 go/no-go 查核表、並記錄回滾計畫。產出 RELEASE-PLAN.md 工件,引導團隊自開發至發布。
於兩種主要策略之間擇定:
依曆(時程箱):
依功能(依範圍):
多數專案採混合法為佳:訂目標日並界定範圍,但留 1-2 週之緩衝。若緩衝期截止仍未達範圍,餘下功能延後。
記錄策略選擇及其理由。
預期: 已記錄發布策略,理由與專案脈絡相符。
失敗時: 若團隊無法達成共識,預設採依曆並備功能優先清單。時程箱迫使優先序之決定。
將發布週期切為含目標日之階段:
## Release Plan: v2.0.0
### Timeline
| Phase | Start | End | Duration | Description |
|---|---|---|---|---|
| Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development |
| Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date |
| Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only |
| RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged |
| RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC |
| RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found |
| Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting |
| Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |
各階段一般時長:
預期: 一張里程碑表,含日期、時長與各階段描述。
失敗時: 若時程過於壓縮(穩定期 < 1 週),延後發布日或縮減範圍。永不省略穩定期。
界定本次發布之「功能凍結」涵義:
### Feature Freeze Criteria
After feature freeze (2026-03-15):
- **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches
- **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security)
- **Exception process**: Feature freeze exceptions require written justification and approval from [release owner]
### Feature Priority List
| Priority | Feature | Status | Owner | Notes |
|---|---|---|---|---|
| P0 (must) | New export format | In progress | [Name] | Blocks release |
| P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement |
| P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready |
| P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |
P0 功能阻擋發布;P1 功能就緒則納入;P2 功能延後而不延期。
預期: 已記錄凍結規則,含例外流程與優先排序之功能清單。
失敗時: 若 P0 功能可能錯過凍結日,立即升級處理。可選:延長開發階段、將該功能切為較小可交付物,或延至點版本(v2.0.1)。
界定候選版本之產生與測試方式:
### Release Candidate Process
1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green
```bash
git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
RC Distribution: Publish RC to staging/testing channel
install.packages("pkg", repos = "https://staging.r-universe.dev/user")npm install pkg@nextRC Testing Period: 5-7 business days
RC Evaluation:
RC2+ Tags: Only if critical issues found in previous RC
git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
**預期:** 已記錄 RC 流程,含標記慣例、發行管道、測試查核表與升級準則。
**失敗時:** 若因壓力而省略 RC 流程,記錄該風險。未經測試之發布回滾機率較高。
### 步驟五:訂 go/no-go 查核表
立發布核准前必達之準則:
```markdown
### Go/No-Go Checklist
#### Must Pass (release blocked if any fail)
- [ ] All CI checks passing on release branch
- [ ] Zero critical bugs open against this version
- [ ] Zero high-severity security vulnerabilities
- [ ] All P0 features verified and documented
- [ ] Changelog complete and reviewed
- [ ] Upgrade path tested from previous version (v1.x -> v2.0.0)
- [ ] License and attribution files up to date
#### Should Pass (release proceeds with documented risk)
- [ ] Zero high bugs open (non-critical)
- [ ] All P1 features included
- [ ] Performance benchmarks within acceptable range
- [ ] Documentation reviewed and spell-checked
- [ ] External dependencies at latest stable versions
#### Decision
- **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked
- **No-Go**: Any "Must Pass" item unchecked
- **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks
預期: go/no-go 查核表,附明確之合格/不合格準則與決策規則。
失敗時: 若 go/no-go 會議結果為 no-go,辨明阻擋項、指派負責人、訂新目標日(通常 1-2 週後),並更新發布計畫。
界定發布若於正式環境造成關鍵問題時之回滾方式:
### Rollback Plan
#### Rollback Triggers
- Critical bug affecting >10% of users
- Data corruption or loss
- Security vulnerability introduced by the release
- Breaking change not documented in changelog
#### Rollback Procedure
1. **Revert package registry**: Unpublish or yank the release
- R/CRAN: Contact CRAN maintainers (cannot self-unpublish)
- npm: `npm unpublish pkg@2.0.0` (within 72 hours)
- GitHub: Mark release as pre-release, publish point fix
2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels
- Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released."
3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible
4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps
#### Point Release Policy
- v2.0.1 for critical bug fixes within 1 week of release
- v2.0.2 for additional fixes within 2 weeks
- Patch releases do not require full RC cycle but must pass CI and critical test suite
將完整發布計畫寫入 RELEASE-PLAN.md 或 RELEASE-PLAN-v2.0.0.md。
預期: 已記錄回滾計畫,含觸發、程序、溝通模板與點版本政策。已寫成完整之 RELEASE-PLAN.md。
失敗時: 若回滾不可行(如資料庫遷移已套用),改記錄向前修補之程序。每次發布皆應有恢復路徑。
apply-semantic-versioning —— 為所規劃之發布判定版本號manage-changelog —— 維護匯入發布說明之變更日誌plan-sprint —— 發布週期之開發階段內的衝刺規劃draft-project-charter —— 專案章程可定義發布路線圖與成功準則generate-status-report —— 追蹤對應發布里程碑之進度