Plan structured release cycle: pick strategy (calendar or feature), set milestones, freeze criteria, RCs, go/no-go, rollback. Output: RELEASE-PLAN.md artifact guiding team dev → release.
Two primary strategies:
Calendar-based (time-boxed):
Feature-based (scope-driven):
Most projects → hybrid: target date + defined scope, 1-2 week buffer. Scope not met by buffer → defer remaining.
Doc strategy choice w/ rationale.
→ Strategy doc'd w/ rationale matching project context.
If err: team can't agree → default calendar-based w/ feature-priority list. Time-box forces prioritization.
Phases w/ target dates:
## Release Plan: v2.0.0
### Timeline
| Phase | Start | End | Duration | Description |
|---|---|---|---|---|
| Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development |
| Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date |
| Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only |
| RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged |
| RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC |
| RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found |
| Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting |
| Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |
Typical durations:
→ Milestone table: dates, durations, descriptions per phase.
If err: timeline too compressed (stabilization < 1 wk) → extend release date or reduce scope. Never skip stabilization.
Define "feature freeze" for this release:
### Feature Freeze Criteria
After feature freeze (2026-03-15):
- **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches
- **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security)
- **Exception process**: Feature freeze exceptions require written justification and approval from [release owner]
### Feature Priority List
| Priority | Feature | Status | Owner | Notes |
|---|---|---|---|---|
| P0 (must) | New export format | In progress | [Name] | Blocks release |
| P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement |
| P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready |
| P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |
P0 → blocks release. P1 → in if ready. P2 → deferred w/o delay.
→ Freeze rules doc'd w/ exception process + prioritized list.
If err: P0 at risk of missing freeze → escalate immediately. Options: extend dev phase, split feature smaller, defer to point release (v2.0.1).
How RCs are produced + tested:
### Release Candidate Process
1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green
```bash
git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
```
2. **RC Distribution**: Publish RC to staging/testing channel
- R: `install.packages("pkg", repos = "https://staging.r-universe.dev/user")`
- Node.js: `npm install pkg@next`
- Internal: Deploy to staging environment
3. **RC Testing Period**: 5-7 business days
- Run full test suite including integration tests
- Verify all P0 features work as documented
- Test upgrade path from previous version
- Check for regressions in existing functionality
4. **RC Evaluation**:
- **No critical/high bugs**: Proceed to release
- **Critical bugs found**: Fix, tag RC2, restart testing period
- **More than 2 RCs needed**: Revisit scope and timeline
5. **RC2+ Tags**: Only if critical issues found in previous RC
```bash
git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
```
→ RC process doc'd: tagging convention, distribution, testing checklist, escalation.
If err: RC skipped (release pressure) → doc the risk. Untested releases → higher rollback prob.
Criteria before release approval:
### Go/No-Go Checklist
#### Must Pass (release blocked if any fail)
- [ ] All CI checks passing on release branch
- [ ] Zero critical bugs open against this version
- [ ] Zero high-severity security vulnerabilities
- [ ] All P0 features verified and documented
- [ ] Changelog complete and reviewed
- [ ] Upgrade path tested from previous version (v1.x -> v2.0.0)
- [ ] License and attribution files up to date
#### Should Pass (release proceeds with documented risk)
- [ ] Zero high bugs open (non-critical)
- [ ] All P1 features included
- [ ] Performance benchmarks within acceptable range
- [ ] Documentation reviewed and spell-checked
- [ ] External dependencies at latest stable versions
#### Decision
- **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked
- **No-Go**: Any "Must Pass" item unchecked
- **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks
→ Go/no-go checklist w/ clear pass/fail + decision rules.
If err: meeting → no-go → ID blockers, assign owners, new target (typically 1-2 wks later), update plan.
Roll back if release causes critical prod issues:
### Rollback Plan
#### Rollback Triggers
- Critical bug affecting >10% of users
- Data corruption or loss
- Security vulnerability introduced by the release
- Breaking change not documented in changelog
#### Rollback Procedure
1. **Revert package registry**: Unpublish or yank the release
- R/CRAN: Contact CRAN maintainers (cannot self-unpublish)
- npm: `npm unpublish pkg@2.0.0` (within 72 hours)
- GitHub: Mark release as pre-release, publish point fix
2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels
- Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released."
3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible
4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps
#### Point Release Policy
- v2.0.1 for critical bug fixes within 1 week of release
- v2.0.2 for additional fixes within 2 weeks
- Patch releases do not require full RC cycle but must pass CI and critical test suite
Write complete plan → RELEASE-PLAN.md or RELEASE-PLAN-v2.0.0.md.
→ Rollback plan doc'd: triggers, procedure, comm template, point release policy. Complete RELEASE-PLAN.md written.
If err: rollback not feasible (DB migration applied) → doc forward-fix instead. Every release needs recovery path.