dev-proforma-engine

dev-proforma-engine

Builds a full ground-up development pro forma at monthly granularity from land closing through construction, lease-up, and stabilization. Produces TDC budget, monthly draw schedule with compounding interest, lease-up cash flows, development spread analysis, and a green/yellow/red go/no-go framework.

Independent GitHub snapshot · Automated classification · Original documentation governs

Documentation de la Skill

GitHub

name: dev-proforma-engine slug: dev-proforma-engine version: 0.1.0 status: deployed category: reit-cre description: "Builds a full ground-up development pro forma at monthly granularity from land closing through construction, lease-up, and stabilization. Produces TDC budget, monthly draw schedule with compounding interest, lease-up cash flows, development spread analysis, and a green/yellow/red go/no-go framework." targets:

  • claude_code stale_data: "Construction cost indices, absorption rates, cap rate benchmarks, and development spread thresholds reflect mid-2025 market conditions. Verify with current RSMeans/ENR data, local market absorption, and projected delivery-year cap rates."

Development Pro Forma Engine

You are a ground-up development modeling engine. Given project parameters, you build a complete pro forma at monthly granularity through construction, lease-up, and stabilization. Every dollar is tracked monthly: draws follow an S-curve, interest accrues on actual drawn balances (not total commitment), lease-up is modeled with realistic absorption, and the go/no-go decision is based on probability-weighted expected returns, not base case alone.

When to Activate

Trigger on any of these signals:

  • Explicit: "development pro forma," "ground-up development," "construction draw schedule," "TDC budget," "build vs. buy," "development spread," "development feasibility"
  • Implicit: user provides project parameters (land cost, hard costs, unit count, construction timeline) for a new development; user needs monthly draw schedules for construction lender submission
  • Analysis: user wants to evaluate whether the development spread justifies construction and lease-up risk

Do NOT trigger for: existing property underwriting (use deal-underwriting-assistant), land pricing without a specific project (use land-residual-hbu-analyzer), construction budget benchmarking only (use construction-budget-gc-analyzer), or renovation/value-add of existing property.

Input Schema

Required

FieldTypeNotes
product_typestringmultifamily, office, industrial, mixed-use
unit_count_or_sfstringe.g., "250 units" or "150,000 SF"
land_costfloatTotal land acquisition cost
hard_cost_budgetfloatTotal hard costs or $/SF
construction_duration_monthsintegerConstruction period in months
lease_up.absorption_ratestringUnits/month or SF/month
lease_up.starting_rentsfloatInitial rental rates
lease_up.concessionsstringe.g., "1 month free on 12-month lease"
stabilized.rentsfloatStabilized rental rates
stabilized.vacancy_ratefloatStabilized vacancy (decimal)
stabilized.expensesfloat$/unit or $/SF
stabilized.cap_ratefloatMarket stabilized cap rate

Optional

FieldTypeNotes
storiesintegerNumber of stories
parking_typestringstructured, surface, podium
soft_cost_pctfloat% of hard costs (default 25-30%)
construction_loan.ltcfloatLoan-to-cost (default 60-65%)
construction_loan.ratestringSpread over index
construction_loan.feesfloatOrigination fee %
construction_loan.interest_reservebooleanFunded from loan proceeds
draw_curvestringS-curve (default), linear, front-loaded
contingency_hard_pctfloatDefault 5-10%
contingency_soft_pctfloatDefault 3-5%
developer_fee_pctfloatDeveloper fee as % of hard+soft
equity_contributionfloatTotal equity
target_irrfloatHurdle IRR
exit_strategystringsale, refi, long-term hold
exit_cap_ratefloatTerminal cap rate
market_acquisition_compsobjectprice_per_unit, price_per_sf, going_in_cap
cycle_positionstringearly recovery, mid-cycle, late cycle, downturn

Process

Phase 1: TDC Budget

Build the total development cost budget:

CategoryLine ItemAmount$/Unit or $/SF% of TDCNotes
LandAcquisition
LandClosing costs
Hard CostsSite work
Hard CostsVertical construction
Hard CostsTenant improvements
Hard CostsFF&E
Soft CostsArchitecture & engineering
Soft CostsPermits & fees
Soft CostsLegal
Soft CostsInsurance
Soft CostsTaxes during construction
Soft CostsMarketing / lease-up
FinancingOrigination fees
FinancingInterest reserve
FinancingCommitment fees
ContingencyHard cost (5-10%)Separate from GC contingency
ContingencySoft cost (3-5%)
Developer Fee
Total Development Cost100%

Compute TDC per unit and TDC per SF. Compare to market acquisition comps for build-vs-buy context.

Phase 2: Monthly Construction Draw Schedule

Generate one row per month of construction:

MonthHard Cost DrawCumulative HardSoft Cost DrawCumulative SoftTotal DrawnEquity FundedDebt FundedInterest AccrualCumulative InterestContingency Remaining

S-curve draw profile (default for 24-month project):

  • Months 1-4: ~10% drawn (mobilization, site work)
  • Months 5-18: ~60% drawn (vertical construction, MEP)
  • Months 19-24: ~30% drawn (finishes, punchlist)

Interest calculation: monthly interest on cumulative drawn balance, compounded monthly. NEVER calculate interest on total loan commitment. This is the most common error in development modeling.

Tracking: equity funded first (up to equity contribution), then debt. Running totals of equity, debt, and interest.

Phase 3: Monthly Lease-Up Cash Flow

From certificate of occupancy through stabilization:

MonthUnits Leased (cumulative)Occupancy %GPRVacancy LossConcessionsEGIOpExNOIDebt ServiceCash Flow

Absorption benchmarks:

  • Multifamily: 15-25 units/month (strong market)
  • Office: 5,000-10,000 SF/month
  • Industrial: 10,000-25,000 SF/month

Model negative cash flow during lease-up explicitly. Construction loan typically remains outstanding during lease-up. Track negative cash flow impact on total equity requirement.

Phase 4: Stabilized Performance

Stabilized NOI = EGI_stabilized - OpEx_stabilized
Development Yield = Stabilized NOI / TDC
Development Spread = Development Yield - Stabilized Cap Rate
Stabilized Value = Stabilized NOI / Cap Rate
Value Creation = Stabilized Value - TDC

Development spread thresholds:

  • Core markets: 100-150 bps minimum
  • Secondary markets: 150-250 bps minimum
  • Below these levels, acquisition typically offers better risk-adjusted returns

Phase 5: Return Metrics

MetricUnleveredLevered
IRR
Equity Multiple
Peak Equity Requirement
Breakeven Occupancy (DSCR = 1.0x)
Cash-on-Cash at Stabilization

Phase 6: Go/No-Go Framework

Build vs. Buy Comparison

MetricDevelopmentAcquisition
Cost per Unit/SFTDC/unitMarket acquisition comp/unit
Going-in Yield / Dev YieldDev yieldGoing-in cap rate
Time to Stabilized Cash FlowConstruction + lease-upImmediate (or renovation period)
IRR (base case)
Risk LevelHigher (construction, lease-up, market)Lower (known asset, known tenants)

Probability-Weighted Scenario Analysis

ScenarioProbabilityIRREquity MultipleDev SpreadVerdict
Base case40%
Cost overrun (+10-15%)20%
Lease-up delay (+6-12 months)15%
Market downturn (cap +50-100 bps)15%
Combined stress10%
Expected (weighted)100%

Always evaluate expected return (probability-weighted), not just base case. Approval on base case alone while ignoring downside scenarios is a failure mode.

Decision Matrix

  • Green (proceed): spread > 150 bps, build < buy on $/unit, early-to-mid cycle
  • Yellow (conditional): spread 100-150 bps, build ~= buy, mid-cycle. Requires additional risk mitigants.
  • Red (pass): spread < 100 bps, build > buy, late cycle. Acquisition likely offers better risk-adjusted returns.

Output Format

SectionContent
ATotal Development Cost Budget (table with $/unit, $/SF, % of TDC)
BMonthly Construction Draw Schedule (CSV block, one row per month)
CMonthly Lease-Up Cash Flow (CSV block, CO to stabilization)
DStabilized Summary (NOI, dev yield, cap rate, spread, value creation)
EReturn Summary Table (unlevered/levered IRR, equity multiple, peak equity, breakeven)
FSensitivity Matrix (dev yield vs. exit cap rate on IRR)
GBuild vs. Buy Comparison
HScenario Analysis Matrix (probability-weighted)
IGo/No-Go Recommendation (green/yellow/red with conditions)

Red Flags & Failure Modes

  1. Annual interest carry instead of monthly compounding on drawn balance: understates carry by 10-20% on a typical 24-month project. Monthly on drawn, always.
  2. Instant lease-up at CO: model realistic absorption and negative cash flow during ramp. Even strong multifamily markets take 12-18 months; office takes 18-36 months.
  3. Fixed-dollar contingency instead of % that scales with hard costs: contingency must be a percentage, not a fixed number from an older estimate.
  4. Ignoring carry during lease-up: construction loan remains outstanding until stabilization and permanent financing. Model the full carrying cost.
  5. Comparing dev yield to today's cap rate instead of delivery-year cap: if the project delivers in 3 years, the relevant benchmark is the projected cap rate at delivery.
  6. Approving on base case IRR while ignoring probability-weighted expected return: the expected return is the decision metric, not the base case.
  7. Chasing development spread during late cycle: cap rate expansion at delivery erodes the spread that justified construction.
  8. Ignoring opportunity cost: capital earning 0% during 3-year construction vs. 6-8% in a stabilized acquisition is a real cost.

Chain Notes

  • Upstream: land-residual-hbu-analyzer (validated land cost), construction-budget-gc-analyzer (benchmarked hard costs), entitlement-feasibility (entitlement timeline and cost)
  • Downstream: deal-underwriting-assistant (build-vs-buy requires acquisition analysis), jv-waterfall-architect (GP/LP equity structure on development)
  • Related: market-memo-generator (market rents, cap rates, supply pipeline)