name: daily-site-diary
description: Build a construction daily site diary or daily report from notes, voice dump, photos, or labour-plant lists. Use when the user says diary, daily report, site report, labour and plant, weather delay, deliveries, or write up today on site.
metadata:
type: workflow
version: "1.0"
pack: construction-office-skills
domain: construction-pm
Daily site diary
A diary is a contemporaneous record. Precision beats prose. If a number was not given, write UNKNOWN — never estimate.
Inputs required
- Project, date, shift, author
- Weather (am/pm) and site condition
- Labour by trade and company (count)
- Plant on site (type + idle/working if known)
- Work performed by area
- Deliveries
- Visitors / consultants / client / certifier
- Delays / disruptions / waiting
- Safety / incidents / permits / isolations
- Photos or photo filenames
- Instructions received on site
Refuse list
- Do not invent headcount, hours, quantities, or plant hours.
- Do not diagnose blame for a delay. Record what was observed.
- Do not turn a diary into a variation claim. Point to
variation-eot-draft if extra work or delay is described.
- Do not omit an incident if the source mentions one.
- Do not send or file. Draft only.
Method
- Date-stamp everything as the source date. If the user is writing next morning, say
Recorded {now} for shift {date}.
- Labour and plant as tables. Subcontractors named if given.
- Work performed = area + activity + constraint. Example:
L2 grid C-D — formwork to soffit — waiting reo inspection.
- Delays get start/finish if known, else
duration UNKNOWN.
- Photo list must include what each photo is supposed to show. If files exist but captions do not, list filenames under Uncaptioned photos.
- Instructions from superintendent / client go in their own section with who said them. These are gold in a dispute.
Output
Follow assets/diary-template.md.
HOLD POINT — not issued to distribution
Optional VET map
Only if asked. Quality record + communications + lessons (if a delay/incident is recorded). No competency claim.
Done when
- Date and author present.
- Every quantity is sourced or UNKNOWN.
- Delays and instructions are isolated from general narrative.