executing-plans
executing-plans
Use when executing an implementation plan in the current session as the implementer yourself — your human partner chose inline execution, or no subagent tool is available
resource-levelerLevel and optimize construction resource allocation across project schedule. Balance labor, equipment usage, and avoid overallocation while maintaining critical path.
Independent GitHub snapshot · Automated classification · Original documentation governs
Optimize resource allocation across construction schedules. Level labor and equipment to avoid peaks, balance workload, and maintain project deadlines while reducing costs.
Resource leveling provides:
from dataclasses import dataclass, field
from typing import List, Dict, Any, Optional, Tuple
from datetime import datetime, date, timedelta
import pandas as pd
import numpy as np
from collections import defaultdict
@dataclass
class Resource:
id: str
name: str
resource_type: str # labor, equipment, material
max_units: float
cost_per_unit: float
unit: str # hours, days, each
@dataclass
class ResourceAssignment:
task_id: str
resource_id: str
units: float
start_date: date
end_date: date
@dataclass
class Task:
id: str
name: str
duration: int # days
start_date: date
end_date: date
predecessors: List[str]
total_float: int
is_critical: bool
resource_assignments: List[ResourceAssignment] = field(default_factory=list)
@dataclass
class LevelingResult:
success: bool
original_end_date: date
leveled_end_date: date
tasks_moved: int
peak_reduction: Dict[str, float]
warnings: List[str]
class ConstructionResourceLeveler:
"""Level resources across construction schedules."""
def __init__(self):
self.resources: Dict[str, Resource] = {}
self.tasks: Dict[str, Task] = {}
self.assignments: List[ResourceAssignment] = []
def add_resource(self, resource: Resource):
"""Add a resource to the pool."""
self.resources[resource.id] = resource
def add_task(self, task: Task):
"""Add a task to the schedule."""
self.tasks[task.id] = task
def add_assignment(self, assignment: ResourceAssignment):
"""Assign a resource to a task."""
self.assignments.append(assignment)
if assignment.task_id in self.tasks:
self.tasks[assignment.task_id].resource_assignments.append(assignment)
def calculate_resource_usage(self, start_date: date = None,
end_date: date = None) -> pd.DataFrame:
"""Calculate daily resource usage."""
if not self.assignments:
return pd.DataFrame()
# Determine date range
if start_date is None:
start_date = min(a.start_date for a in self.assignments)
if end_date is None:
end_date = max(a.end_date for a in self.assignments)
# Create date range
dates = pd.date_range(start_date, end_date, freq='D')
# Initialize usage matrix
usage = {r_id: [0.0] * len(dates) for r_id in self.resources}
# Fill in usage
for assignment in self.assignments:
if assignment.resource_id in usage:
for i, d in enumerate(dates):
if assignment.start_date <= d.date() <= assignment.end_date:
usage[assignment.resource_id][i] += assignment.units
df = pd.DataFrame(usage, index=dates)
df.index.name = 'date'
return df
def identify_overallocations(self) -> List[Dict]:
"""Identify resource overallocations."""
usage = self.calculate_resource_usage()
overallocations = []
for resource_id, resource in self.resources.items():
if resource_id in usage.columns:
daily_usage = usage[resource_id]
over_days = daily_usage[daily_usage > resource.max_units]
if len(over_days) > 0:
overallocations.append({
'resource_id': resource_id,
'resource_name': resource.name,
'max_units': resource.max_units,
'peak_usage': daily_usage.max(),
'over_by': daily_usage.max() - resource.max_units,
'days_overallocated': len(over_days),
'first_overallocation': over_days.index[0].date(),
'worst_day': daily_usage.idxmax().date()
})
return overallocations
def level_resources(self, method: str = 'float_priority',
protect_critical_path: bool = True,
max_extension: int = 30) -> LevelingResult:
"""Level resources to resolve overallocations."""
original_end = max(t.end_date for t in self.tasks.values())
tasks_moved = 0
warnings = []
# Get initial overallocations
initial_over = self.identify_overallocations()
if not initial_over:
return LevelingResult(
success=True,
original_end_date=original_end,
leveled_end_date=original_end,
tasks_moved=0,
peak_reduction={},
warnings=["No overallocations found"]
)
# Track peak usage before
usage_before = self.calculate_resource_usage()
peaks_before = {r: usage_before[r].max() for r in usage_before.columns}
# Leveling loop
iteration = 0
max_iterations = len(self.tasks) * 2
while iteration < max_iterations:
iteration += 1
overallocations = self.identify_overallocations()
if not overallocations:
break
# Find task to move
moved = False
for over in overallocations:
resource_id = over['resource_id']
worst_day = over['worst_day']
# Find tasks using this resource on worst day
candidates = self._find_movable_tasks(
resource_id, worst_day, protect_critical_path
)
if candidates:
# Sort by priority (lowest float first to preserve options)
candidates.sort(key=lambda t: -t.total_float)
task_to_move = candidates[0]
# Calculate new dates
new_start, new_end = self._calculate_shift(
task_to_move, resource_id, max_extension
)
if new_start:
self._shift_task(task_to_move.id, new_start, new_end)
tasks_moved += 1
moved = True
break
if not moved:
warnings.append("Could not resolve all overallocations")
break
# Calculate results
usage_after = self.calculate_resource_usage()
peaks_after = {r: usage_after[r].max() for r in usage_after.columns}
peak_reduction = {}
for r in peaks_before:
if r in peaks_after:
reduction = (peaks_before[r] - peaks_after[r]) / peaks_before[r] * 100
peak_reduction[r] = reduction
leveled_end = max(t.end_date for t in self.tasks.values())
if leveled_end > original_end + timedelta(days=max_extension):
warnings.append(f"Project extended beyond max allowed ({max_extension} days)")
remaining_over = self.identify_overallocations()
return LevelingResult(
success=len(remaining_over) == 0,
original_end_date=original_end,
leveled_end_date=leveled_end,
tasks_moved=tasks_moved,
peak_reduction=peak_reduction,
warnings=warnings
)
def _find_movable_tasks(self, resource_id: str, on_date: date,
protect_critical: bool) -> List[Task]:
"""Find tasks that can be moved to reduce overallocation."""
candidates = []
for task in self.tasks.values():
# Check if task uses this resource on this date
uses_resource = any(
a.resource_id == resource_id and
a.start_date <= on_date <= a.end_date
for a in task.resource_assignments
)
if not uses_resource:
continue
# Check if critical path protected
if protect_critical and task.is_critical:
continue
# Check if has float
if task.total_float > 0:
candidates.append(task)
return candidates
def _calculate_shift(self, task: Task, resource_id: str,
max_extension: int) -> Tuple[date, date]:
"""Calculate optimal shift for a task."""
resource = self.resources[resource_id]
# Try shifting forward
for days in range(1, min(task.total_float + 1, max_extension + 1)):
new_start = task.start_date + timedelta(days=days)
new_end = task.end_date + timedelta(days=days)
# Check if this resolves overallocation
temp_usage = self._calculate_usage_if_moved(task.id, new_start, new_end)
if temp_usage.get(resource_id, 0) <= resource.max_units:
return new_start, new_end
return None, None
def _calculate_usage_if_moved(self, task_id: str, new_start: date,
new_end: date) -> Dict[str, float]:
"""Calculate resource usage if task were moved."""
# Simplified: calculate peak on affected dates
usage = defaultdict(float)
for assignment in self.assignments:
if assignment.task_id == task_id:
# Use new dates
for d in pd.date_range(new_start, new_end):
usage[assignment.resource_id] = max(
usage[assignment.resource_id],
assignment.units
)
else:
# Use existing dates
for d in pd.date_range(assignment.start_date, assignment.end_date):
usage[assignment.resource_id] = max(
usage[assignment.resource_id],
assignment.units
)
return dict(usage)
def _shift_task(self, task_id: str, new_start: date, new_end: date):
"""Shift a task to new dates."""
task = self.tasks[task_id]
delta = new_start - task.start_date
# Update task
task.start_date = new_start
task.end_date = new_end
# Update assignments
for assignment in self.assignments:
if assignment.task_id == task_id:
assignment.start_date += delta
assignment.end_date += delta
def optimize_crew_size(self, resource_id: str,
target_utilization: float = 0.85) -> Dict:
"""Recommend optimal crew size for a resource."""
usage = self.calculate_resource_usage()
if resource_id not in usage.columns:
return None
daily_usage = usage[resource_id]
resource = self.resources[resource_id]
# Calculate statistics
peak = daily_usage.max()
avg = daily_usage.mean()
working_days = (daily_usage > 0).sum()
# Current utilization
current_util = avg / resource.max_units if resource.max_units > 0 else 0
# Optimal size for target utilization
optimal_size = avg / target_utilization
return {
'resource_id': resource_id,
'current_max_units': resource.max_units,
'peak_usage': peak,
'average_usage': avg,
'working_days': int(working_days),
'current_utilization': current_util,
'recommended_max_units': round(optimal_size, 1),
'potential_savings': (resource.max_units - optimal_size) * resource.cost_per_unit * working_days
}
def generate_histogram(self, resource_id: str) -> pd.DataFrame:
"""Generate resource histogram data."""
usage = self.calculate_resource_usage()
if resource_id not in usage.columns:
return pd.DataFrame()
resource = self.resources[resource_id]
df = pd.DataFrame({
'date': usage.index,
'usage': usage[resource_id].values,
'capacity': resource.max_units,
'overallocated': usage[resource_id].values > resource.max_units
})
return df
def generate_report(self) -> str:
"""Generate resource leveling report."""
lines = ["# Resource Leveling Report", ""]
lines.append(f"**Generated:** {datetime.now().strftime('%Y-%m-%d %H:%M')}")
lines.append(f"**Resources:** {len(self.resources)}")
lines.append(f"**Tasks:** {len(self.tasks)}")
lines.append("")
# Overallocations
overallocations = self.identify_overallocations()
if overallocations:
lines.append("## Overallocations Found")
for over in overallocations:
lines.append(f"\n### {over['resource_name']}")
lines.append(f"- **Max Units:** {over['max_units']}")
lines.append(f"- **Peak Usage:** {over['peak_usage']}")
lines.append(f"- **Days Overallocated:** {over['days_overallocated']}")
lines.append(f"- **Worst Day:** {over['worst_day']}")
else:
lines.append("## No Overallocations")
lines.append("All resources are within capacity.")
# Resource utilization
lines.append("\n## Resource Utilization")
for resource_id in self.resources:
opt = self.optimize_crew_size(resource_id)
if opt:
lines.append(f"\n### {self.resources[resource_id].name}")
lines.append(f"- **Utilization:** {opt['current_utilization']:.1%}")
lines.append(f"- **Peak:** {opt['peak_usage']:.1f}")
lines.append(f"- **Average:** {opt['average_usage']:.1f}")
return "\n".join(lines)
from datetime import date
# Initialize leveler
leveler = ConstructionResourceLeveler()
# Add resources
leveler.add_resource(Resource(
id="CARP",
name="Carpenters",
resource_type="labor",
max_units=10,
cost_per_unit=75,
unit="hours"
))
# Add tasks
leveler.add_task(Task(
id="T1",
name="Frame Level 1",
duration=10,
start_date=date(2026, 3, 1),
end_date=date(2026, 3, 14),
predecessors=[],
total_float=5,
is_critical=False
))
# Add assignments
leveler.add_assignment(ResourceAssignment(
task_id="T1",
resource_id="CARP",
units=8,
start_date=date(2026, 3, 1),
end_date=date(2026, 3, 14)
))
# Check overallocations
overallocations = leveler.identify_overallocations()
for over in overallocations:
print(f"{over['resource_name']}: {over['peak_usage']} vs {over['max_units']} max")
# Level resources
result = leveler.level_resources(protect_critical_path=True)
print(f"Tasks moved: {result.tasks_moved}")
print(f"End date change: {result.original_end_date} -> {result.leveled_end_date}")
# Generate report
print(leveler.generate_report())
pip install pandas numpy