apqpAdvanced Product Quality Planning (APQP) — plan and track a new product launch through all 5 phases, identify deliverables per phase, run gate reviews, and ensure quality outputs are complete before Start of Production (SOP). Use when launching a new part, managing an APQP project, or auditing APQP completeness. Covers AIAG APQP 2nd edition and IATF 16949 §…
Independent GitHub snapshot · Automated classification · Original documentation governs
Use this skill when:
Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Plan & Define → Product Design → Process Design → Product & Process → Feedback &
& Development & Development Validation Corrective Action
↓ ↓ ↓ ↓ ↓
Program Prototype Pre-launch PPAP SOP +
approval build build submission Production
All phases run with concurrent engineering — phases overlap and teams work in parallel.
Objective: Understand customer requirements and define what the product must do.
Key deliverables:
| Deliverable | Description |
|---|---|
| Voice of the Customer (VOC) | Customer wants, needs, expectations — translated to measurable requirements |
| Design Goals | Product performance targets derived from VOC |
| Reliability and Quality Goals | Target failure rate, warranty targets, Cpk targets |
| Preliminary Bill of Materials | Draft BOM from design intent |
| Preliminary Process Flow | High-level process sequence |
| Preliminary Special Characteristics | Initial list of critical/significant characteristics |
| Product Assurance Plan | Quality plan for the programme |
| Management Support | Signed-off programme charter with resources and timing |
Gate 1 pass criteria:
Objective: Translate customer requirements into a product design with verified characteristics.
Key deliverables:
| Deliverable | Description |
|---|---|
| DFMEA | Design FMEA — all failure modes analysed, H-AP items addressed |
| Design Verification Plan (DVP) | Test plan linked to DFMEA failure modes |
| Drawing and Specification Release | Fully released engineering drawings and 3D data |
| Material Specifications | Raw material specs, supplier approval plan |
| Drawing and Specification Changes | Change management process in place |
| New Equipment and Tooling | List of new equipment/tooling required |
| Special Product and Process Characteristics | Updated with design detail |
| Gauge Plan | MSA requirement list — which characteristics need MSA studies |
| Prototype Control Plan | Control plan for prototype builds |
| Prototype Build | Prototype parts manufactured and tested |
| Engineering Drawings | Released and approved |
Gate 2 pass criteria:
Objective: Design and verify the manufacturing process.
Key deliverables:
| Deliverable | Description |
|---|---|
| Packaging Standards | Packaging design, labelling, MMOG/LE if required |
| Product/Process Quality System Review | Internal quality system audit against customer requirements |
| Process Flow Chart | Detailed process flow for all operations |
| Floor Plan Layout | Manufacturing floor layout approved |
| Characteristics Matrix | Matrix linking process steps to product characteristics |
| PFMEA | Process FMEA — all failure modes, AP ratings, H-AP actions complete |
| Pre-Launch Control Plan | Control plan for pre-launch production |
| Process Instructions | Work instructions for all operations |
| MSA Plan | Gauge R&R plan for all measurement systems |
| Preliminary Process Capability Study Plan | Plan for capability studies on special characteristics |
| Packaging Specifications | Final packaging specs including OEM labelling |
Gate 3 pass criteria:
Objective: Validate the production process and prepare for PPAP submission.
Key deliverables:
| Deliverable | Description |
|---|---|
| Production Trial Run | Significant Production Run (minimum run to PPAP requirements) |
| MSA Studies | Gauge R&R completed for all special characteristics |
| Preliminary Process Capability | Cpk study on special characteristics (target ≥ 1.67) |
| Production Part Approval (PPAP) | All 18 PPAP elements complete and submitted |
| Production Validation Testing | Final validation tests on production parts |
| Packaging Evaluation | Production packaging validated |
| Production Control Plan | Final production control plan approved |
| Quality Planning Sign-Off | Customer approval of PPAP and APQP completion |
| Management Support Sign-Off | Internal management approval for SOP |
Gate 4 pass criteria (= PPAP approval):
Objective: Continuous improvement after SOP — close the loop on any issues found in production.
Key activities:
| Activity | Description |
|---|---|
| Reduced variation | Monitor process capability, reduce common-cause variation |
| Improved customer satisfaction | Track warranty, field returns, and customer scorecards |
| Improved delivery and service | Monitor OTD (on-time delivery) and logistics performance |
| Lessons learned | Document lessons learned for future programmes |
| Control Plan updates | Update based on production data and any quality escapes |
| PFMEA updates | Update based on field failures and warranty data |
Phase 5 is ongoing. There is no defined end gate — it runs for the life of the programme.
| Milestone | Typical timing before SOP |
|---|---|
| Programme approval / Phase 1 complete | 18–24 months |
| Design release / Phase 2 complete | 12–15 months |
| Process design complete / Phase 3 complete | 8–10 months |
| PPAP submission | 4–6 months |
| PPAP approval (customer) | 3–4 months |
| Pre-production builds | 2–3 months |
| SOP | 0 |
Automotive OEM programmes vary — always confirm with the customer's APQP coordinator.
At each gate review, verify:
Gate reviews are STOP gates — do not advance until all criteria are met.
At the start of each use, ask the user:
"How would you like to receive the output? A — Structured Markdown (formatted tables and sections, ready to copy) B — Plain tables (simplified structure for Excel or Word) C — Narrative report (flowing text for a formal document or email)
Default: A."
Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.
| Version | Date | Author | Change |
|---|---|---|---|
| 1.0 | 2026-06-06 | @RBraga01 | Initial release |
| 1.1 | 2026-06-06 | @migmcc | Added 300-part production trial run minimum to Gate 4 criteria and Common Mistakes |