eurosys-workflowUse when planning a EuroSys campaign end to end — choosing between the spring and fall gates of an edition, backward-scheduling system building and evaluation from the abstract deadline, handling the notification-to-revision-to-resubmission pipeline, and landing camera-ready, artifacts, and April travel for the conference.
Independent GitHub snapshot · Automated classification · Original documentation governs
Use this as the project plan around a EuroSys submission. The venue's calendar
is its most distinctive constraint: one April conference fed by two
submission gates roughly four months apart. Dates below are the EuroSys 2027
cycle as rendered on 2026-07-08 (2027.eurosys.org/cfp.html); re-pull the live
CFP before committing the team to any of them.
| Milestone | Date | Status on 2026-07-08 |
|---|---|---|
| Spring abstracts / papers | May 7 / May 14, 2026 | Closed |
| Spring notification | August 21, 2026 | ~6 weeks away |
| Fall abstracts / papers | September 17 / 24, 2026 | ~10 / 11 weeks away |
| Fall notification | January 29, 2027 | — |
| Camera-ready (both cohorts) | ~March 5, 2027 (third-party, 待核实) | — |
| Conference, Rabat, Morocco | April 19–23/24, 2027 (end date 待核实) | — |
So a team starting today has one live target: the fall gate. A team with a spring submission under review is in the quiet zone — the right use of that zone is artifact preparation and boundary experiments, both of which pay off regardless of the August outcome.
T-10w now System feature-frozen for the paper's claims; eval matrix written
T-8w late Jul Decomposition + cost experiments running nightly; plots automated
T-6w mid Aug Full draft exists in acmart[sigplan] review mode; internal read #1
T-4w late Aug Boundary/worst-case runs done; related-work sweep incl. dblp pass
T-3w early Sep External mock review by a systems colleague outside the project
T-2w Sep 10 Claims-to-evidence audit; every number has provenance
T-1w Sep 17 ABSTRACT GATE — title/abstract/authors/topics/conflicts final
T-0 Sep 24 Paper gate — identity sweep on the final PDF, upload with margin
The two-gate structure is a gift: the abstract week is for polishing, and the title and abstract registered at T-1w determine which reviewers bid — write them for bidding, not as placeholders.
eurosys-author-response).eurosys-topic-selection has the routing table).| Risk | Early symptom | Owner |
|---|---|---|
| Eval starts too late | No automated plots by T-8w | Experiments lead |
| Baseline dispute | Tuning provenance undocumented | Whoever runs baselines |
| Anonymity leak | Repo/PDF never swept | Submission owner |
| Revision-condition overrun | No feasibility call in week one | Project lead |
| Travel/visa for Rabat | Unchecked entry requirements post-accept | Presenting author |
The two-gate calendar creates long author-side silences (submission to notification is ~14 weeks). Teams that treat them as vacations pay later:
Groups with multiple projects should stagger them across the two gates rather than crowding the fall: a spring submission gets its decision in August with time to revise into the fall, while a fall submission's revision path crosses into the next edition. Maturity at gate time — not preference for a season — should pick the gate.
[Live target] <gate and days remaining>
[Stage now] building / evaluating / drafting / submitted / revising / accepted
[Backward-plan health] <milestones behind or on track>
[Post-notification branch] <accept / revision / reject plan sketch>
[Owners] <risk -> named person>