sap-pp

sap-pp

This skill handles SAP PP (Production Planning) including MRP, production orders, process orders, shop floor control, capacity planning, BOM management, routing, and PP-PI for process industries. Use when user mentions PP, MRP, MD01, MD04, production order, CO01, CO11N, MFBF, BOM, routing, work center, capacity, planned order, operation, confirmation, goods…

Independent GitHub snapshot · Automated classification · Original documentation governs

Skill 문서

GitHub

name: sap-pp description: > This skill handles SAP PP (Production Planning) including MRP, production orders, process orders, shop floor control, capacity planning, BOM management, routing, and PP-PI for process industries. Use when user mentions PP, MRP, MD01, MD04, production order, CO01, CO11N, MFBF, BOM, routing, work center, capacity, planned order, operation, confirmation, goods issue, backflush, MRP Live, MPS, demand management, scheduling, process order, PP-PI, KANBAN. allowed-tools: Read, Grep

1. MRP (Material Requirements Planning)

Planning Run

  • MD01 (ECC / S/4HANA): classic MRP run → plant-level or single material
  • MD01N (S/4HANA): MRP Live → HANA-optimized, faster, recommended
  • MD02: single-item, multi-level MRP (for testing / selective re-planning)
  • MD03: single-item, single-level

MRP Types (Material Master MRP 1 view)

TypeDescription
PDMRP — demand-driven (standard)
VBManual reorder point
VMAutomatic reorder point
NDNo MRP
MFMake-to-order (individual requirements)

Lot Sizing Procedures

KeyDescription
EXLot-for-lot (exact demand quantity)
FXFixed lot size
WBWeekly lot size
MBMonthly lot size
HBReplenishment up to maximum stock level

Exception Messages (MD04)

ExceptionMeaningAction
10Reschedule inMove order earlier
15Reschedule outPush order later
20Firm planned order — rescheduleEvaluate manually
25SurplusCancel or reduce
30New order requiredConvert planned order

2. Production Order

Lifecycle

CO01 (Create) → Release (CO02 / KOAB batch) → Goods Issue (MIGO 261)
→ Confirmation (CO11N) → Final Confirmation → TECO (technically complete)
→ Settlement (KO88) → CLSD (closed)

Key T-codes

T-codeDescription
CO01Create production order
CO02Change production order
CO03Display production order
CO11NProduction order confirmation
CO13Cancel confirmation
CO24Missing parts list (component shortage)
COOISProduction order information system
MIGOGoods issue (261) / GR (101) for order

Goods Issue

  • Manual: MIGO → movement type 261 → production order number
  • Backflush: CO11N → backflush checkbox → automatic at confirmation
  • Partial GI: allowed — tracks remaining requirements in MD04

Settlement

  • KO88: individual order → settlement to: cost center / G/L / material (product cost collector)
  • KO8G: collective settlement → mass processing
  • Always simulate first → check receivers and amounts before actual posting
  • Variance categories: input price / input quantity / output price / output quantity / remaining input

3. Process Orders (PP-PI)

Used in: chemical, pharmaceutical, food & beverage industries

T-codeDescription
COR1Create process order
COR2Change process order
COR6NProcess order confirmation
CORKPI sheet (process instruction) execution
CORZProcess order scheduling

Process instructions (PI sheets): define what operators enter during production Master recipe (C201): replaces routing for process industries


4. BOM Management

Key T-codes

T-codeDescription
CS01Create BOM
CS02Change BOM
CS03Display BOM
CS11BOM explosion (multi-level)
CS14BOM comparison
CS15Where-used list

BOM Usages

UsageDescription
1Production
2Engineering / design
3Universal
5Sales
6Costing
  • Alternative BOMs: same material, multiple production methods (alt. 1, 2, 3...)
  • Selection method: MRP 4 view → BOM explosion / selection method

5. Routing and Work Centers

Work Center (CR01 / CR02)

  • Define: capacity category, available capacity, costing formulas, scheduling formulas
  • Capacity: CR11 → available capacity per shift (machine / labor)

Routing (CA01 / CA03)

  • Operations: sequence → work center → standard values (setup / machine / labor time)
  • Control key: determines: confirmation required / goods movement / costing / scheduling

Reference Operation Sets (CA11)

  • Reusable operation templates → assign to multiple routings

6. Capacity Planning

T-codeDescription
CM01Capacity load overview (work center)
CM21Capacity leveling (interactive)
CM50Variable capacity planning
CM99Scheduling overview
  • Finite scheduling: material's MRP considers capacity constraints
  • Infinite scheduling: MRP ignores capacity → capacity leveling done separately
  • Bottleneck analysis: CM50 → identify overloaded work centers

7. Demand Management

  • MD61: planned independent requirements (make-to-stock strategy)
  • MD62: change planned independent requirements
  • Strategy group (MRP 3 view): determines how sales orders consume PIRs
    • Strategy 10: make-to-stock (no individual requirements)
    • Strategy 20: make-to-order (each order = separate production)
    • Strategy 40: planning with final assembly

8. S/4HANA PP Changes

FeatureECCS/4HANA
MRP runMD01MD01N (MRP Live) recommended
MRP performanceSlower (sequential)Parallel HANA-based
Exception handlingMD04 listEnhanced exception management
Scheduling boardCM21Production Scheduling Board (Fiori)
Shop floorCOOISManufacturing Execution Fiori apps
eWM integrationExternal WMEmbedded eWM (same system)
pMRPNot availablePredictive MRP (AI-based exception detection)