generate-status-reportGenerate a project status report by reading existing artifacts (charter, backlog, sprint plan, WBS), calculating metrics, identifying blockers, and summarizing progress with RAG indicators for schedule, scope, budget, and quality. Use at the end of a sprint or reporting period, when stakeholders request a health update, before steering committee or governan…
Independent GitHub snapshot · Automated classification · Original documentation governs
析項目成品、算進度、摘成就阻滯與後續、以 RAG(紅/琥/綠)健康指示生週期狀況報告。
掃項目目錄察 PM 成品:
讀可得檔。非必皆存——報告依可得資料適應。
得: 至少一成品成功讀取,要指標已抽。
敗則: 無成品則無法生報告。先以 draft-project-charter 或 manage-backlog 技能創章程或待辦。
自可得資料算指標:
敏捷指標(BACKLOG.md / SPRINT-PLAN.md):
經典指標(WBS.md):
## Metrics
| Metric | Value | Previous | Trend |
|--------|-------|----------|-------|
| Velocity | [N] pts | [N] pts | ↑/↓/→ |
| Sprint Completion | [N]% | [N]% | ↑/↓/→ |
| Backlog Remaining | [N] pts | [N] pts | ↓ (good) |
| Schedule Variance | [+/-N days] | [+/-N days] | |
得: 三至五指標已算,與前期比。
敗則: 若無歷史資料(首報),略 Previous 與 Trend 列。若資料不全,於報告腳注標間隙,附行動項以立跟蹤。
列活動阻滯與風險:
## Blockers & Risks
| ID | Type | Description | Severity | Owner | Status | Action Required |
|----|------|------------|----------|-------|--------|----------------|
| R-001 | Risk | [Description] | High | [Name] | Open | [Action] |
| B-001 | Blocker | [Description] | Critical | [Name] | Active | [Action by date] |
| I-001 | Issue | [Description] | Medium | [Name] | Investigating | [Action] |
交叉比對章程風險登記。標任何前未識之新風險。
得: 所有活動阻滯與頂風險皆記,附擁者與行動。
敗則: 若無阻滯,顯陳「無活動阻滯」——勿留空。阻滯無擁者則升至項目經理指派。
書二節:
## Accomplishments (This Period)
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
- [Completed item/milestone with evidence]
## Planned (Next Period)
- [Planned item/milestone with target]
- [Planned item/milestone with target]
- [Planned item/milestone with target]
得: 三至五成就附具體證據,下期三至五計劃項。
敗則: 若無成就,報原因(受阻、重劃、隊不可得)。若下期計劃不明,列「計劃會排於 [日]」為主項。
四維度察項目健康:
| Dimension | Green | Amber | Red |
|---|---|---|---|
| Schedule | On track or ahead | 1-2 weeks behind | >2 weeks behind or milestone missed |
| Scope | No uncontrolled changes | Minor scope adjustments | Scope creep affecting deliverables |
| Budget | Within 5% of plan | 5-15% over plan | >15% over plan or untracked |
| Quality | Tests pass, criteria met | Minor quality issues | Critical defects or acceptance failures |
書完整報告:
# Status Report: [Project Name]
## Report Date: [YYYY-MM-DD]
## Reporting Period: [Start] to [End]
## Document ID: SR-[PROJECT]-[YYYY-MM-DD]
### Overall Health
| Dimension | Status | Notes |
|-----------|--------|-------|
| Schedule | 🟢/🟡/🔴 | [One-line explanation] |
| Scope | 🟢/🟡/🔴 | [One-line explanation] |
| Budget | 🟢/🟡/🔴 | [One-line explanation] |
| Quality | 🟢/🟡/🔴 | [One-line explanation] |
### Executive Summary
[2-3 sentences: overall status, key achievement, biggest risk]
### Metrics
[From Step 2]
### Accomplishments
[From Step 4]
### Blockers & Risks
[From Step 3]
### Planned Next Period
[From Step 4]
### Decisions Needed
- [Decision 1 — needed by date, from whom]
---
*Report prepared by: [Name/Agent]*
存為 STATUS-REPORT-[YYYY-MM-DD].md。
得: 完整狀況報告存,含 RAG 指示、指標、敘述。
敗則: 若資料不足為 RAG 評估,用 ⚪(灰)示「資料不足」,列下期須收集之資料。
draft-project-charter — 章程供狀況跟蹤之里程與成功準則manage-backlog — 待辦指標入狀況報告plan-sprint — 衝刺結果供速度與完成資料create-work-breakdown-structure — WBS 完成驅動經典進度指標conduct-retrospective — 狀況報告資料入回顧