hpca-workflowUse when planning an HPCA project timeline from venue fit through the two-step July registration and paper gate, the autumn review wait, the single rebuttal/revision window, notification, IEEE camera-ready, artifact evaluation, and the February/March talk, with backward-planning offsets for a hardware-evaluated paper.
Independent GitHub snapshot · Automated classification · Original documentation governs
Use this as the project-management skill for an HPCA submission. Replace every date with the current official timetable and plan backward from the late-July gate.
HPCA is a conference, not a journal: it has no standing editor-in-chief and no article-processing charge. It is run by the IEEE-CS Technical Committee on Computer Architecture (TCCA); the rotating leadership is the per-edition General and Program Chairs (HPCA 2027 program chairs were reported as Aamer Jaleel and Mattan Erez — 待核实), and the cost model is registration fees. Chairs rotate yearly, so re-check the current organization page rather than carrying a name forward.
HPCA sits in the winter seat: a late-July deadline feeds an autumn review and a February/March conference. It is the last major architecture deadline of the summer, so a project that misses it waits for MICRO's spring gate or ISCA's November gate — plan the fallback before you need it.
| Weeks out (heuristic) | Hardware-evaluated milestone |
|---|---|
| 8+ | Mechanism implemented; fidelity contract (tool, config, workloads) fixed |
| 6 | Baseline sweeps complete; per-workload results, not just means |
| 4 | Real-silicon or validated-simulator numbers logged with machine state |
| 3 | Full draft in the IEEE two-column template |
| 2 | Internal mock review by an architecture-minded reader |
| 1 | Reference author-list check, anonymity sweep, artifact mirror assembled |
| 0 | Registration then paper on HotCRP |
These offsets are planning heuristics — anchor every one to the current official timetable, never to a previous cycle.
[Current stage] idea / evaluation / writing / registration / paper / window / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <page/anonymity/instrument/reproducibility/artifact/presentation>
[Fallback venue] <MICRO / ISCA / ASPLOS branch if rejected>
[Owner map] <task -> person or role>