sigcomm-workflowUse when planning an ACM SIGCOMM project timeline around the single yearly deadline — venue fit, evidence lock, abstract registration and paper upload in February, the early-reject/rebuttal/one-shot-revision review pipeline, shepherd-run camera-ready, TAPS proceedings, artifact evaluation, and forward planning for the next edition.
Independent GitHub snapshot · Automated classification · Original documentation governs
Use this as the project-management skill for a SIGCOMM campaign. The defining constraint is one main-track deadline per year feeding one August conference: there is no fall gate, so the plan is a year-long backward schedule from February, not a two-shot hedge. Replace every date with the current official timetable.
SIGCOMM is a conference, not a journal: it has no standing editor-in-chief and no article-processing charge. The rotating leadership is the per-edition General Chairs and Program Committee Co-Chairs (the 2026 roster was not retrievable on 2026-07-09 — 待核实), and the cost model is registration, not APCs; proceedings publish through ACM TAPS into the ACM Digital Library. Chairs rotate yearly, so re-check the current organization page.
| Weeks out (heuristic) | Systems/measurement milestone |
|---|---|
| 14+ | Mechanism designed; testbed or trace pipeline standing and repeatable |
| 10 | Core evaluation runs producing stable tails across repeated trials |
| 7 | Baselines that fight back implemented and tuned fairly |
| 5 | Full draft in ACM two-column format, figures counting against 12 pages |
| 3 | Internal mock review by a networking-minded reader; break-point experiment added |
| 2 | Reproducibility ledger and artifact skeleton assembled |
| 1 | Anonymity sweep, HotCRP fields, abstract registered |
| 0 | Full paper uploaded AoE; receipt re-read |
These offsets are planning heuristics — anchor each to the current official timetable, never to a previous edition's calendar.
Because the deadline is annual, the calendar after submission matters as much as before it. As of 2026-07-09 the SIGCOMM 2026 cycle is in its live post-decision phase: the February deadline passed, decisions issued, and the work now is camera-ready finalization, shepherd sign-off, artifact evaluation, and the August presentation — while the next edition's February deadline is already the horizon for new work. Plan both halves: the run-up to the single deadline, and the shepherd-to-proceedings tail that follows acceptance.
[Current stage] idea / evaluation / writing / abstract / submission / rebuttal / revision / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <format / anonymity / evaluation realism / reproducibility / shepherd>
[Owner map] <task -> person or role>