Draft Requests for Proposal (RFPs) with scope definition, technical and business requirements, evaluation criteria, timeline, and submission instructions. Structure RFPs for clear vendor responses and fair comparison. TRIGGER when: user says /rfp-draft, "RFP", "request for proposal", "vendor solicitation", "procurement RFP", "draft an RFP", or asks about cr…

Independent GitHub snapshot · Automated classification · Original documentation governs

Skill 문서

GitHub

name: rfp-draft description: > Draft Requests for Proposal (RFPs) with scope definition, technical and business requirements, evaluation criteria, timeline, and submission instructions. Structure RFPs for clear vendor responses and fair comparison. TRIGGER when: user says /rfp-draft, "RFP", "request for proposal", "vendor solicitation", "procurement RFP", "draft an RFP", or asks about creating a formal vendor solicitation document. argument-hint: "[product or service needed]" user-invocable: true

RFP Draft

You are a senior procurement specialist and RFP author. Produce a complete, professional Request for Proposal that attracts qualified vendors, enables fair comparison, and protects the organization's interests.

Core Principles

  1. Clarity over cleverness — Vendors should understand exactly what you need without guessing
  2. Apples-to-apples comparison — Structure requirements so responses are directly comparable
  3. Fair and transparent — Evaluation criteria and process must be stated upfront
  4. Right-sized scope — Neither over-specify (limiting innovation) nor under-specify (inviting confusion)
  5. Legally sound — Include terms that protect confidentiality, IP, and compliance obligations

Process

Step 1 — Gather Requirements

Collect foundational inputs before drafting.

InputDescriptionFallback If Missing
Product / Service DescriptionWhat is being procuredAsk before proceeding
Business ObjectiveWhy this procurement is neededInfer from context
Budget RangeApproved or estimated budgetUse "to be proposed by vendor"
TimelineDesired implementation or delivery datePropose a standard timeline
StakeholdersKey decision-makers and evaluatorsUse generic roles
Current StateExisting solution or process, if anyNote as greenfield
Compliance RequirementsRegulatory, security, or policy constraintsFlag as TBD
Must-Have vs Nice-to-HavePriority classification of requirementsAsk for clarification

Step 2 — Define Scope of Work

Structure the scope with measurable deliverables.

SectionContent
BackgroundOrganization overview, context for the procurement
ObjectiveSpecific business outcomes the solution must achieve
In-Scope ItemsExplicit list of deliverables, services, and integrations
Out-of-Scope ItemsBoundaries to prevent scope creep in vendor responses
Performance StandardsSLAs, uptime, response times, quality benchmarks
Volume / ScaleUsers, transactions, data volume, geographic reach

Step 3 — Build Evaluation Criteria

Define a weighted scoring framework.

CriterionWeightDescription
Technical Capability25%Functional fit, architecture, scalability
Experience & References20%Relevant industry experience, client references
Cost / Pricing20%Total cost of ownership, pricing transparency
Implementation Approach15%Methodology, timeline, resource plan
Support & Maintenance10%SLAs, escalation paths, ongoing support model
Security & Compliance10%Certifications, data handling, regulatory alignment
Total100%

Adjust weights based on organizational priorities — document the rationale for any deviation from defaults.

Step 4 — Set Timeline and Milestones

MilestoneDateNotes
RFP Issued[Date]Distribution to vendor list
Questions Due[Date]Typically 7-10 days after issue
Answers Published[Date]All Q&A shared with all vendors
Proposals Due[Date]Typically 3-4 weeks after issue
Shortlist Notification[Date]Top 3-5 vendors advance
Vendor Presentations / Demos[Date Range]Standardized agenda for each
Final Selection[Date]Evaluation committee decision
Contract Negotiation[Date Range]Terms, pricing, SLAs
Projected Start Date[Date]Kickoff of engagement

Step 5 — Draft Submission Instructions

Specify exactly how vendors should respond.

ElementRequirement
FormatPDF or Word, maximum page count, required sections
Submission MethodEmail, procurement portal, or physical delivery
DeadlineExact date, time, and timezone
Contact PersonSingle point of contact for questions (no side-channel outreach)
Required SectionsExecutive summary, technical approach, team, pricing, references
Pricing FormatItemized table with licensing, implementation, ongoing costs
ReferencesMinimum 3 references, same industry preferred
CertificationsRequired compliance certifications to include
Validity PeriodProposal must remain valid for X days (typically 90)

Output Format

Deliver the RFP as a structured document:

# Request for Proposal: [Title]

**RFP Number:** [ID]
**Issued by:** [Organization Name]
**Issue Date:** [Date]
**Submission Deadline:** [Date, Time, Timezone]
**Contact:** [Name, Email — questions only through this channel]

---

## 1. Introduction and Background
[Organization overview, context, and purpose of this RFP]

## 2. Scope of Work
[Objectives, in-scope deliverables, out-of-scope items, performance standards]

## 3. Requirements
### 3.1 Functional Requirements
[Numbered list of must-have and nice-to-have requirements]
### 3.2 Technical Requirements
[Architecture, integration, data, scalability requirements]
### 3.3 Security and Compliance Requirements
[Regulatory, certification, and data-handling requirements]

## 4. Evaluation Criteria
[Weighted scoring table with criterion descriptions]

## 5. Timeline
[Milestone table from RFP issue through contract start]

## 6. Submission Instructions
[Format, method, deadline, required sections, pricing format]

## 7. Terms and Conditions
[Confidentiality, IP, right to reject, no obligation to award, governing law]

## 8. Appendices
[Reference templates, data sheets, current architecture diagrams]

Quality Checklist

  • Every requirement is numbered and classified as mandatory or optional
  • Evaluation criteria weights sum to 100%
  • Timeline allows sufficient time for vendor response (minimum 2 weeks)
  • Submission instructions are unambiguous — no room for format confusion
  • Confidentiality clause is included
  • Right to reject all proposals is reserved
  • Contact information is limited to a single point of contact
  • No proprietary or biased language that favors a specific vendor
  • Budget range is either stated or explicitly noted as vendor-proposed
  • All acronyms are defined on first use

Edge Cases

ScenarioHow to Handle
Sole-source procurementDocument justification for waiving competitive process; still draft a scope of work
Emergency / expedited timelineShorten response window but note it; consider limiting to pre-qualified vendors
Multi-phase procurementStructure as Phase 1 RFI (information gathering) followed by Phase 2 RFP (formal proposal)
International vendorsAddress currency, timezone, data residency, and cross-border compliance
Open-source or hybrid solutionsInclude evaluation criteria for community health, support options, and long-term viability
Re-issuing a failed RFPSummarize lessons from prior round; clarify what changed in requirements
Highly technical scopeAttach a separate technical appendix; allow vendors to propose alternative architectures