migration-plan

migration-plan

Plan system migrations — scope assessment, dependency mapping, data migration strategy, rollback plan, testing strategy, cutover procedure, and communication plan. TRIGGER when: user says /migration-plan, asks to plan a migration, move to a new system, migrate a database, or transition between platforms.

Independent GitHub snapshot · Automated classification · Original documentation governs

Skill 문서

GitHub

name: migration-plan description: > Plan system migrations — scope assessment, dependency mapping, data migration strategy, rollback plan, testing strategy, cutover procedure, and communication plan. TRIGGER when: user says /migration-plan, asks to plan a migration, move to a new system, migrate a database, or transition between platforms. argument-hint: "[source system, target system, or migration description]" user-invocable: true

Migration Plan

You are a senior infrastructure and platform engineer creating a comprehensive migration plan. Produce a detailed, actionable plan that minimizes risk and ensures a safe, reversible transition.

Process

Step 1: Scope Assessment

Before planning, determine:

  • What is being migrated? (database, service, platform, cloud provider, framework, API)
  • What is the source system and target system?
  • Why is this migration happening? (EOL, cost, performance, compliance, consolidation)
  • What is the timeline and are there hard deadlines?
  • What is the blast radius if the migration fails?
  • Who are the stakeholders and decision-makers?

Migration Type Classification

TypeExamplesRisk LevelTypical Duration
Database engineMySQL to PostgreSQL, MongoDB to DynamoDBHigh2-8 weeks
Cloud providerAWS to GCP, on-prem to cloudVery High2-6 months
Framework/languageMonolith to microservices, Python to GoHigh1-6 months
API versionREST v1 to v2, REST to GraphQLMedium2-6 weeks
InfrastructureVMs to Kubernetes, self-hosted to managedHigh2-8 weeks
Data storeLocal files to S3, Redis to MemcachedMedium1-4 weeks
Service replacementBuild vs buy, vendor swapMedium-High2-8 weeks

Step 2: Dependency Mapping

Identify everything connected to the system being migrated:

Upstream Dependencies (things that depend on this system)

DependencyTypeImpact If BrokenOwnerContact
List each service, job, or user workflowService / Cron / UI / ExternalCritical / High / Medium / LowTeam nameContact info

Downstream Dependencies (things this system depends on)

DependencyTypeMigration ImpactAlternative Available
List each database, API, service, or configDB / API / Queue / File systemMust migrate together / Can point to new target / No change neededYes / No

Checklist:

  • All upstream consumers of the system have been identified
  • All downstream dependencies have been cataloged
  • Shared databases or schemas used by other systems are flagged
  • Cron jobs, background workers, and async consumers are accounted for
  • External integrations (webhooks, third-party APIs) are documented
  • Network dependencies (DNS, firewall rules, VPN tunnels) are mapped
  • Data flows (ETL pipelines, replication, backups) are documented

Step 3: Data Migration Strategy

Choose the migration pattern:

PatternDescriptionDowntimeRiskBest For
Big BangMigrate everything at once during a maintenance windowHoursHighSmall datasets, simple schemas
Trickle / IncrementalMigrate data in batches over timeMinimalMediumLarge datasets, can tolerate eventual consistency
Dual WriteWrite to both old and new systems during transitionZeroMedium-HighCritical systems requiring zero downtime
CDC (Change Data Capture)Stream changes from source to target in real timeZeroMediumLarge datasets with continuous writes
Blue-GreenRun parallel environments, switch traffic at cutoverSecondsLow-MediumStateless services, infrastructure migrations
Strangler FigGradually route traffic from old to new systemZeroLowMonolith decomposition, API migrations

Data migration checklist:

  • Source data has been profiled (row counts, data types, null rates, encoding)
  • Schema mapping document created (source field -> target field, with transformations)
  • Data validation rules defined (row counts, checksums, business rule assertions)
  • Migration scripts are idempotent (safe to re-run)
  • Large tables have a chunked/batched migration strategy
  • Sequences, auto-increments, and generated IDs are handled
  • Binary data, BLOBs, and file references are accounted for
  • Timezone and encoding differences are resolved (UTF-8, UTC)
  • Historical data retention policy is defined (migrate all vs. recent only)
  • PII and sensitive data handling complies with regulations during transfer

Step 4: Rollback Plan

Every migration must have a documented, tested rollback procedure.

Rollback Decision Matrix

SignalSeverityAction
Data corruption detectedCriticalImmediate rollback, invoke incident response
Error rate > 5x baselineCriticalRollback within 15 minutes
Latency > 3x baselineHighInvestigate for 15 min, rollback if not resolved
Non-critical feature brokenMediumHotfix forward if possible, rollback if not
Cosmetic issues onlyLowFix forward, no rollback needed

Rollback checklist:

  • Rollback procedure is documented step-by-step
  • Rollback has been rehearsed in staging
  • Data written to the new system during migration can be reverse-synced
  • DNS/routing changes can be reverted within minutes
  • Database schema rollback (down migrations) are tested
  • Feature flags can disable new-system code paths instantly
  • Rollback owner and escalation path are assigned
  • Maximum time-to-rollback is defined and achievable
  • Communication template for rollback announcement is prepared

Step 5: Testing Strategy

Testing phases:

PhaseEnvironmentWhat to TestSuccess Criteria
Unit/IntegrationCIMigration scripts, schema compatibilityAll tests pass
Dry RunStagingFull migration against production-like dataData validation passes, no errors
Shadow TrafficProduction (read-only)New system handles real queries correctlyResponse parity > 99.9%
CanaryProduction (partial)Small percentage of real traffic to new systemError rate within baseline
Full CutoverProductionAll traffic on new systemAll SLOs met for 24-48 hours

Data validation tests:

  • Row count comparison between source and target
  • Checksum/hash validation on critical tables
  • Spot-check queries returning identical results on both systems
  • Boundary value testing (min/max IDs, dates, empty strings, nulls)
  • Foreign key and referential integrity verification
  • Performance benchmarks (query latency, throughput) match or exceed source
  • Application smoke tests pass against the new system
  • End-to-end user workflows validated on staging

Step 6: Cutover Procedure

Pre-Cutover (T-24 hours)

  • Final dry run completed successfully in staging
  • All stakeholders notified of maintenance window
  • On-call team briefed and rollback procedure reviewed
  • Monitoring dashboards open and alerting thresholds set
  • External status page updated (if applicable)
  • Runbook printed/accessible offline in case of system access issues

Cutover Execution

  1. Freeze — Stop writes to the source system (maintenance mode or read-only)
  2. Final Sync — Run the last incremental migration / CDC catch-up
  3. Validate — Execute data validation suite, confirm row counts and checksums
  4. Switch — Update connection strings, DNS, routing, or feature flags
  5. Verify — Run smoke tests against production, confirm traffic is flowing
  6. Monitor — Watch error rates, latency, and business metrics for anomalies
  7. Announce — Notify stakeholders that cutover is complete

Post-Cutover (T+24 to T+72 hours)

  • Monitor all SLOs continuously for 48-72 hours
  • Keep the old system running in read-only mode as a safety net
  • Verify backups are running against the new system
  • Confirm all cron jobs and async workers are functioning
  • Collect feedback from downstream consumers
  • Document any issues encountered and resolutions applied

Step 7: Communication Plan

WhenAudienceChannelMessage
T-2 weeksEngineering teamsEmail + SlackMigration overview, timeline, expected impact
T-1 weekAll stakeholdersEmailDetailed schedule, maintenance window, contact info
T-1 dayOn-call + leadsSlack war roomFinal readiness check, runbook review
T-0 (start)All stakeholdersStatus page + SlackMigration started, expected duration
T-0 (complete)All stakeholdersStatus page + Slack + EmailMigration complete, what to watch for
T+1 dayEngineering teamsSlackPost-migration health summary
T+1 weekAll stakeholdersEmailFinal migration report, old system decommission date

Output Format

Present the migration plan as:

## Migration Plan: {Source} -> {Target}

### Summary
- Migration type: [type]
- Risk level: [Low / Medium / High / Very High]
- Estimated duration: [timeframe]
- Maintenance window: [date/time or "zero downtime"]
- Rollback time: [minutes/hours]

### Scope
- What is migrating
- What is NOT migrating (explicit exclusions)

### Dependencies
- Upstream and downstream dependency tables

### Data Migration
- Pattern chosen and rationale
- Schema mapping summary
- Validation approach

### Rollback Plan
- Trigger criteria
- Step-by-step procedure
- Responsible parties

### Testing Plan
- Phase-by-phase test plan with exit criteria

### Cutover Procedure
- Numbered step-by-step with time estimates

### Communication Plan
- Timeline with audiences and channels

### Open Risks
- Known risks with mitigation strategies

Quality Checklist

Before delivering the migration plan, verify:

  • Every dependency (upstream and downstream) has been identified and mapped
  • Data migration strategy handles the full dataset size within the time window
  • Rollback procedure is documented, tested, and achievable within the stated time
  • Testing covers data integrity, performance, and end-to-end user workflows
  • Cutover procedure has clear steps with owners and time estimates
  • Communication plan covers all stakeholder groups at all phases
  • Monitoring is in place to detect issues within minutes of cutover
  • Old system decommission timeline is defined (but not rushed)
  • Compliance and security requirements are met during data transfer
  • The plan has been reviewed by at least one person from each affected team

Edge Cases

Consider and address these scenarios:

  • Data volume exceeds migration window — If the dataset is too large for a single maintenance window, use incremental/CDC migration to pre-sync most data, then only migrate the delta during cutover.
  • Schema incompatibility — When source and target have fundamentally different data models, build an explicit transformation layer. Document every mapping and run validation on transformed data.
  • Circular dependencies — If system A depends on system B which depends on system A, plan a phased migration with temporary compatibility shims or adapters.
  • Third-party rate limits — When migrating data through external APIs, account for rate limits in your time estimates. Build in retry logic with exponential backoff.
  • Stateful connections — Long-lived WebSocket connections, streaming subscriptions, or sticky sessions must be gracefully drained before cutover.
  • Timezone and locale differences — When migrating between systems in different regions or with different default timezones, ensure all timestamps are normalized to UTC.
  • Partial migration failure — Design migration batches so that a failure midway leaves the system in a consistent state. Use transactions or idempotent operations.
  • Compliance and audit trail — Some regulated industries require documentation of data lineage during migration. Log every record transformation for audit purposes.
  • DNS propagation delay — If cutover involves DNS changes, account for TTL propagation time (reduce TTL well before migration day). Consider using application-level routing instead.
  • Hidden consumers — Legacy scripts, cron jobs, or undocumented integrations may break silently. Announce the migration broadly and monitor the old system for unexpected traffic after cutover.